Given the information below for a one year project please help with the questions that follows:
PV is Planned ValueEV is Earned valueAC is actual costBAC is budget at Completion
PV = $23,000EV = $20,000AC = $25,000BAC = $120,000
a. What is the cost variance, schedule variance and cost performance index (CPI), and schedule performance index (SPI) for the project?b. How is the project doing? Is it ahead of schedule or behind schedule? It is under budget or over budget?c. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?d. Use the schedule performance index (SPI) to estimate how long it will take to finish the project.
Program that displays information about a family member
Discuss with others what kinds of the data are considered volatile and the methods through which the investigators should collect and preserve the volatile data. Recognize the consequences of not collecting or preserving the volatile data to the i..
Using three D flip-flops,a multiplexer,decoders and gates, construct a 3-bit Gray code counter that has two inputs: reset, which sets the counter to 000, and inc, which makes the counter go to the next value in the sequence.
explain the development of network architectures and its subsequent consolidation over past 20 years. Include topologies and the TCP/IP, Internetwork Packet Exchange/Sequence Packet Exchange (IPX/SPX), Network Basic Input Output System (NetBIOS), ..
Select a topic related to some aspect of the Software Engineering. Write about 2500+ word (minimum) paper on that particular topic-single spaced 12 pt times or times new roman font.
Explain the data and record structures for the vertex ordering and vertex or edge colouring (or labelling) and a suitably the greedy graph search algorithm in order to solve each of the following problems in time bound indicated.
Implement this function in the assembly language and write down a test program which calls function many times, passing it several values. Show all results on screen and include screen shots of the outputs.
Explain why is the global economy so vital today? Explain how the global economy has altered since the mid-twentieth century.
How would you recommend that your IT department prepare for disaster.
Write down a program which prompts the user to enter a telephone number expressed in the letters and outputs corresponding telephone number in digits.
Write down a java program, which build a binary tree
Explain the term peer-to-peer networking? Describe why is bit torrent regarded to be a more efficient protocol? In the bit torrent context, explain how seeders and the leechers work.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd