Reference no: EM132561774
Question 1. The labor yield variance equals
a. (Inputs allowed - inputs used) x budgeted weighted-average materials unit price for the planned mix.
b. (Budgeted weighted-average labor rate for planned mix - budgeted weighted-average labor rate for actual mix) x inputs used.
c. (Inputs allowed - inputs used) x budgeted weighted-average labor rate for the planned mix.
d. (Budgeted weighted-average materials unit cost for planned mix - budgeted weighted-average materials unit cost for actual mix) x inputs used.
Question 2. The labor mix variance equals
a. (Inputs allowed - inputs used) x budgeted weighted-average materials unit price for the planned mix.
b. (Budgeted weighted-average labor rate for planned mix - budgeted weighted-average labor rate for actual mix) x inputs used.
c. (Inputs allowed - inputs used) x budgeted weighted-average labor rate for the planned mix.
d. (Budgeted weighted-average materials unit cost for planned mix - budgeted weighted-average materials unit cost for actual mix) x inputs used
Question 3. The materials yield variance equals
a. (Inputs allowed - inputs used) x budgeted weighted-average materials unit price for the planned mix.
b. (Budgeted weighted-average labor rate for planned mix - budgeted weighted-average labor rate for actual mix) x inputs used.
c. (Inputs allowed - inputs used) x budgeted weighted-average labor rate for the planned mix.
d. (Budgeted weighted-average materials unit cost for planned mix - budgeted weighted-average materials unit cost for actual mix) x inputs used.