Reference no: EM132942471
Construction ContractsWinter Company constructs office buildings in Ellensburg. It began a $50,000,000, 3-year contract on January 1, 2018. The following information is available regarding this contract.
2018 2019 2020
Costs incurred during current year $ 12,000,000 $ 20,000,000 $ 13,000,000
Estimated costs to complete at year end 28,000,000 10,000,000 0
Progress billings during year 10,000,000 18,000,000 22,000,000
Collections on billings during year 8,000,000 17,000,000 25,000,000
Required:
Problem a. Assuming Winter uses the percentage-of-completion method, calculate the gross profit to be recognized in 2018 and 2019.
Problem b. Assuming Winter uses the percentage-of-completion method, indicate how the contract would be presented on Winter's income statement for the year ended December 31, 2019.
Problem c. Assuming Winter uses the completed-contract method, calculate the gross profit to be recognized in 2020.
Problem d. Assuming Winter uses the completed-contract method, indicate how the contract would be presented on Winter's balance sheet (Accounts Receivable and Construction-in-process) for the year ended December 31, 2019.
Problem e. Assuming Winter uses the completed-contract method and billings in 2019 are $40,000,000 instead of $18,000,000, what will be the effect on the balance sheet in 2019?