Question: Peter Minn is planning to go to the Department of Motor Vehicles to have his driver's license renewed. His friend, Patricia, who is accompanying him, is applying for a new license. In both cases there are five steps that are required:
(A) having a picture taken,
(B) signing a signature verification form,
(C) passing a written test,
(D) passing an eye test, and
(E) passing a driving test.
For renewals the steps are performed in the order A, B, C, D, and E with average times required, respectively, of 0.2, 0.1, 0.3, 0.2, and 0.6 hour. In the case of new applications, the steps are performed in the sequence D, B, C, E, and A, with average times required of 0.3, 0.2, 0.7, 1.1, and 0.2 hour, respectively. Peter and Pat go on a day when the department is essentially empty. How should they plan their schedule in order to minimize the time required for both to complete all five steps?
|
Find the total time for both to complete their advising
: Mary and Marcia Brown are two sisters currently attending university together. Each requires advising in five subjects: history, English, mathematics, science.
|
|
Determine the load combinations for the permanent
: Determine the load combinations for the permanent, imposed and superimposed loads-Provide the required bending moment, shear and axial force diagrams
|
|
Truth based sales culture
: "Truth based sales culture". What is the importance of this? please explain with an example
|
|
Prepare three sigma controlchart for both production process
: Prepare a three-sigma control chart for both production processes, using the new and standard material.
|
|
How should they plan schedule in order to minimize time
: Peter Minn is planning to go to the Department of Motor Vehicles to have his driver's license renewed. His friend, Patricia, who is accompanying him.
|
|
What is the standard deviation of the production
: The amount of milk produced by dairy cows depends on number of factors, including average temperature and rainfall. What is standard deviation of the production
|
|
Find the expected completion time of all eight jobs
: A computer center has two identical computers for batch processing. The computers are used as parallel processors. Job times are estimated by the user.
|
|
Separation of powers affect administrative decision making
: In what ways does the separation of powers affect administrative decision making? Does it promote the rational-comprehensive approach, incrementalism,
|
|
Evaluate the factors of demand and supply
: FINA3324 Investment Analysis: "Buy or rent?" Assignment. Evaluate the factors of demand and supply that will cause house and rent prices to fluctuate
|