Question - Syarikat Harapan Cerah Bhd acquired a 20-hectare piece of land in January 2018 at a cost of RM10 million, with the intention to develop the land to become a new city at Batu Kawan, Penang. Other costs incurred to buy the land are professional fees RM250,000 and stamp duties RM50,000. The company also incurred another RM500,000 in levelling and clearing the land.
The company intends to develop the land in two phases: Phase I and Phase II. Phase I is taking up 5 hectares for the construction of single-storey house and Phase II is taking up 10 hectares for the construction of bungalow. The balance of 5 hectares is used to develop a common area.
Construction work commenced on 1 March 2018 and expected to complete by year 2020. The financial data for 2018 financial year are as follows:
|
Phase I (single storey)
|
Phase II (bungalow)
|
Units to be developed
|
100 units
|
50 units
|
Unit sold
|
40 units
|
30 units
|
Selling price per unit
|
RM 300,000
|
RM 500,000
|
Development costs incurred to date
|
RM2,000,000
|
RM3,000,000
|
Common cost allocated
|
RM1,636,364
|
RM3,000,000
|
Estimates of development costs to complete
|
RM4,000,000
|
RM8,000,000
|
Required -
1. Determine percentage of completion for Phase I and II using the cost-to-cost basis (Round up your answer to 1 decimal point).
2. Prepared a partial Statement of Profit and Loss for the year ended 2018 showing the amount of revenue and expenses to be recognized. (Round up your answer to the nearest RM).
3. Assume the company cannot determine the percentage of completion reliably, how should the company recognize its revenue during year 2018?