How peter preferred strategy or strategies

Assignment Help Project Management
Reference no: EM133320423

Hunter Engineering was established in 1936 and is now a public limited company in which the Hunter familyowned the controlling interest. lt relied solely on Government Contracts as primary source of business. Untilthe late 1990s. contracts had been placed on a "cost plus basis, but with the government's shift in policytowards reductions in public expenditure, the method of placing contracts had been changed to "fxed price'Sizes of the contracts were reduced. Instead of relying solely on large contracts involving over a hundredemployees or more for up to 5 years, the company handled contracts that frequently involved less than 15employees for a duration of under two years. Having projects at the right stafhng levels and effhciency drivesmeant that between 1998 and 2012, employee levels had fallen from 1.500 to 720. Staffng levels in theElectrical Engineering Department fell from 45 to 26 over the same period. Between 2012 and 2017, furtherorganisational restructuring initiatives resulted in the loss of over 170 employees.

Peter Green, Project Manager in Electrical Engineering, had joined the company in 1987 as a relatively youngsenior electrical engineer in his early 30s, and for the frst ten years of his employment at Hunter Engineeringhe worked on just 2 very large projects, each spanning 5 years. He had not enjoyed this long-term projectcommitment, so was relieved to fnd himself transferred to smaller projects because of more proiects withower staff levels. After working on 16 smaller projects in various capacities, frst as the Project Team Leader,and later as a full Project Manager, he was promoted to Small Projects Director in January 2017. His promotioncoincided with the company's decision to rename itself Hunter Engineering Group, a signal that it intended todiversify going forward.

Going commercial

January 2018, Peter put forward his ideas to expand the Electrical Department by going commercial andtendering for contracts outside the Government Defense Portfolio. While this had received the agreement orhis Divisional Head, Peter was well aware of the problems facing smaller commercial projects in a companywhere operations had to be defined solely by government interests and requirements.

The company had very high fxed overheads, but more importantly the highly demanding Quality AssuranceSystem, a mandatory for government defense work meant rigid processes that included time-consumingGovernment contracts. For example, every deviation from the issued drawing had to be recorded andapproved with a dated electronic signature from the Head of the Design Unit. Thus, any scope for iudgementwas not permitted by the inspection engineers. Peter realised that one of his frst problems was to introducesome scope for judgement if small commercial projects were to be viable.

Hunter Engineering Group had no experience in tendering for commercial projects. Government contractsrequired very strict and complex approval process, which include documentation with contributions from aldepartments. lt would therefore require considerable effort on Peter's part to prevent these departments fromgetting in the way when it came to new commercial ventures, particularly as most departments were lookingfor work - due to the downturn in recent government projects.

Peter was also concerned about staffng levels. The Electrical Engineering Department's involvement in minoiprojects could be anything from 3 months to 2 years in duration. Yet extra staff could only be recruited if itcould be shown that there would still be a shortage in twelve months' time. The Electrical EngineeringDepartment was always 25 percent understaffed due to difhculties involved in the forward planning of theworkload. Recruitment policy remained unchanged. Peter estimated a need for 6 more engineers. Staff moralewas falling. New graduates that joined required training. The senior engineers in the department were havingto spend more and more time training the new graduates. Although there was a dearth of experiencedengineers between the 25 to 40 age group, these qualifed engineers found higher paying positions outsideHunter Engineering. While new graduates saw their 20-year age gap between themselves and their seniorsand felt that promotion was impossible, so they left at the earliest possible moment.

The Sales Operations Team was also a serious cause for concern for Peter. lt was staffed by ex-governmentemployees who responded to general staff requirements issued by the Government Department. They solconly components and products which the company had already manufactured and approved by thegovernment regulators. They did not explore the market to assess its future needs, nor did they initiate anyinternal research and development activity.

A further problem arose in the Manufacturing Department. The continuity of large projects meant that thestaff employed at the end of one fscal year would be employed only at the start of next year. The FinanceDepartment therefore had become accustomed to delaying the issue of engineering and manufacturing ordeinumbers by up to 6 weeks into the new fscal year.

The HR Department moved slowly. Several weeks could elapse between an interview and the issue of an offelof employment. They seemed unconcerned that experienced engineers were at a premium and that newgraduates steadily left Hunter after two years, thus continuing to exacerbate the age gap. Peter's currentengineering staff on small commercial projects numbered 4 where 3 were new graduates with less than 6months' professional experience, and one was an engineer with merely five years' experience

As such Peter is determined to get more work into the department and to increase staff levels in order tohandle it. He is particularly determined to initiate action change. His priority was to write a change proposal tothe Senior Executive Team, via his Divisional Head. He needs change and he developed a change plan to theElectrical Department by going commercial

Questions

1. What economic, political and culture issues are raised? Justify your answer with evidence from the case.

2. What are the relevant change concepts, theories, and frameworks that can be applied to this case? Provide at least two and justify the relevance of each theory.

3. Outline a change plan demonstrating how Peter preferred strategy or strategies could be put forward toaddress the issues and problems in this case. Provide a brief outline of each strategy and a timeline for theexecution of Peter's proposed implementation plan. Don't forget to include evaluation and maintenanceactions in Peter's plan.

Reference no: EM133320423

Questions Cloud

Dealing with potential product safety problems : Develop a plan of action for dealing with potential product safety problems that can be persuasively presented to top management.
How does supply chain for pink lady at apples in the u.s. : How does supply chain for Pink Lady® apples in the U.S. and or Europe including all players from nurseries to end customers.
What is the central theme of daniel kwan : ENG 4990 California State University, What is the central theme of Daniel Kwan and Daniel Scheinert's film, Everything Everywhere All at Once, how does the film
Discuss global supply chain management knoweldge : Discuss global supply chain management knoweldge how she could better understand how the existing supply chain strategy was creating problems for the company.
How peter preferred strategy or strategies : Outline a change plan demonstrating how Peter preferred strategy or strategies could be put forward toaddress the issues and problems in this case.
Pumped upfeed water distribution system arrangements : The downfeed, hydro-pneumatic, and pumped upfeed water distribution system arrangements are typically used only for mid- to high-rise buildings.
How retailers would ease bullwhip effect during the pandemic : Discuss how retailers would ease the bullwhip effect during the Global pandemic. Make use of relevant examples from the case study to support your answer.
What type of merger and acquisition : What type of Merger and Acquisition? What attributes associated with successful acquisition strategy of your researched company? Explain.
Write thee strategix importance of innovation : Basicall We have to write thee strategix importance of innovation, the nature of innovatio, innovation as a process, innovation and entreprenuership, Innovation

Reviews

Write a Review

Project Management Questions & Answers

  Pros and cons of six software systems

As part of the management team for PPQ Parts manufacturing company, you are tasked with selecting the best software packages for the firm's materials requirements planning (MRP), capacity requirement planning (CRP), and enterprise resource plannin..

  Develop a budget template for the project

Develop a budget template for the project in your scenario According to the already presented WBS and develop a BSC which includes your suggested KPIs in the four BSC categories for the project in your scenario.

  Describe leader expectations and set standards for employee

In an organization, frameworks that describe leader's expectations and set standards for employee conduct are called

  What is the charitable trust doctrine

Do you think that enforcement of antitrust laws should be aggressive or lenient for health services industry mergers? Support your position.

  Why makers have not adopted voluntary emissions standards

Why do you think motorcycle makers have not adopted voluntary emissions standards? Should they have done so? Why or why not?

  How do they add value through implementation of the four ps

Pick your favorite product, service provider, or retailer. How do they add value through the implementation of the four Ps?

  What service aspects are provided with the product

What service aspects are provided with the product? -How is customer service handled?  - What elements of service quality can your firm focus on?

  Explain bundle of sticks idea as it relates to real property

Explain the bundle-of-sticks idea as it relates to real property.- Explain the five possessory interests in land.- Explain the bundle-of-sticks idea as it relates to intellectual property.

  Describe the process you would use to deal

Write the dialog that would occur at the team meeting as you describe the process you would use to deal with this situation.

  What opportunity costs must be considered in project

What opportunity costs must be considered in project selection? What other criteria would be important in project selection?

  What direction to take your company in the future

What types of AI systems could you use to generate information that would be useful to you in deciding what direction to take your company in the future?

  What is the weighted average cost of capital

The cost of equity is 14%, the cost of debt is 9%, and the tax rate is 34%. What is the weighted average cost of capital?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd