Reference no: EM132495713
February 1, 2018, Salisbury Company purchased land for the future factory location at a cost of $82,000. The dilapidated building that was on the property was demolished so that construction could begin on the new factory building. The new factory was completed on November 1, 2018.
Costs incurred during this period were:
Amount
Demolition dilapidated building - $2,800
Architect Fees - $11,250
Legal Fees - for title search - $1,500
Interest During Active Construction Period - $5,025
Real estate transfer tax - $1,350
Construction Costs - $605,000
Question 1: Using this information, how much should be recorded as the cost of the land?