How much safety stock should they consider

Assignment Help Project Management
Reference no: EM132398549

Annual demand for binders at The Stationeers is 10,000 units. They operate 250 days per year. It takes 5 days to get an order from the supplier. They like to have a service level of 96%. Standard deviation of demand during lead time is 10 units.

How much safety stock should they consider?

What is the Reorder Point?

Reference no: EM132398549

Questions Cloud

Importance of validating these environmental scans : The purpose of the scanning this data is to determine the usefulness. What would be the importance of validating these environmental scans?
What cleaning and recoding of the variables did you do : Find a publicly available secondary dataset that will allow you to answer at least one of your research question for your proposal.
How much safety stock should be held : How much safety stock should be held? What reorder point should be used?
How much safety stock should they consider : How much safety stock should they consider? What is the Reorder Point?
How much safety stock should they consider : How much safety stock should they consider? What is the Reorder Point?
What is the eoq for these binders : Annual demand for binders at The Stationeers is 10,000 units. Each binder costs $5. It costs $10 to place an order, and annual holding costs are 25% of an item'
Shareholder value creation : Assess Caterpillar Inc. to determine whether their top focus is accounting profitability, shareholder value creation, or economic value creation.
What are the major sources of risk facing the company : Identify the controllable and uncontrollable elements that Starbucks has encountered in entering global markets and What are the major sources of risk facing
Define what is your reaction to the changes in price : Views of price elasticity is different for teenagers than adults. Thinking back to when you were a teenager, were you more or less price sensitive.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd