How much it will cost to complete the project

Assignment Help Operation Management
Reference no: EM133251228

Gautrain Project: briefing

The Gautrain Project delegation provided background information on the Gautrain Rapid Rail Link Project. Following this, they provided an overview of the proposed Gautrain system. It was estimated that approximately 130 000 passenger trips would be made on the Gautrain each day. It was noted that the Project would be conducted through a public private partnership. The Bombela Consortium had been selected as the preferred bidder, and it was hoped that the final contract would be signed in late 2005. If this took place, construction could begin in early 2006. It was hoped that the entire project would be completed by April/May 2010. The estimated cost of the Gautrain was R 20 million. However, this estimate probably would not rise any further as the contract with the Bombela Consortium would be a fixed cost contract. The delegation added that the Gautrain would form part of an integrated provincial transport system. A Departmental delegation briefly outlined their view of the Gautrain Project. Cabinet had not yet approved financial assistance for the Gautrain Project. It first wanted to ensure that the Project would lead to economic development, promote investment in infrastructure, contribute to South Africa's transport system; alleviate the use of private cars; and create jobs. The Department noted that Cabinet would be taking a decision on the Gauteng Project before the end of the year.

In the ensuing discussion, Members raised issues around the Gautrain Project and the 2010 World Cup. It was noted that there were no legal obligations on South Africa to complete the Gautrain by the 2010 World Cup. Members also enquired about certain details surrounding the public private partnership and funding. Some Members were concerned that government would perhaps be burdened with an unequal share of the risk. Members also enquired why the Metrorail could not be updated to operate rapid link trains; what the provincial patronage guarantee entailed; how many sustainable jobs would be created; and whether the middle-class target market would use the train. The Committee was also concerned about the huge expense of the Project. There were other transport issues, relating to the needs of poorer commuters, which also needed to be addressed.

The Chairperson noted that the Committee had been following the developments around the Gautrain Project. To date, the Gautrain Project had been conducted as a provincial initiative and, as a result, most of the oversight work had been undertaken by the provincial legislature and local government authorities. Nonetheless, the Committee had called the Gautrain Project to Parliament because it was of national interest.

The Chairperson stated that Cabinet would be taking a decision on whether to commence with the Gautrain Project during December. Indeed, it was possible that construction on the Gautrain could begin in January 2006. Ideally, the Committee would have wanted greater engagement with the Gautrain Project, but due to time constraints this would not be possible.

The Chairperson noted that the Minister of Finance had stated that the Gautrain Project would cost approximately R 20 billion. However, the entire 2004/05 transport budget was only R 4.67 billion. This money would be spent to ensure that six to seven million passengers a day received some form of transport. He noted that public transport was under-capitalised and, at times, unsafe. Indeed, there was an ongoing crisis with transport in South Africa. In the light of this crisis, the Committee needed to be responsible in its approach to the Gautrain Project.

The Chairperson noted that the Tshwane, Johannesburg, and Ekurhuleni municipalities officially supported the Gautrain Project. Nonetheless, during a Committee oversight visit to Johannesburg and Tshwane certain municipal officials had privately, and in their personal capacity, expressed reservations about the Gautrain Project. They felt that it complicated their spatial planning. Nonetheless, they felt that the Gautrain Project would commence, despite their reservations. Added to this, certain concerns about the Gautrain Project had been raised in the City of Johannesburg's Integrated Transport Plan. Similar sentiments were also expressed in the Tshwane Integrated Transport Plan. In fact, the Tshwane Plan stated that the City supported the Gautrain Project, despite their perception that there was little consultation. The Committee's caution appeared to be shared by some other entities, but for different reasons. Indeed, the estimated costs of the Gautrain Project had risen over the years. In addition, there was now a certain degree of pressure for the Gautrain Project to be undertaken. The Chairperson added that one perhaps needed to guard against the Gautrain Project being used by other provinces as a precedent to embark on similar projects.

Mr J Van Der Merwe (Gautrain Project Leader) provided background information to the Gautrain Project. This included highlighting the objectives of the Gautrain Project, which were to alleviate severe road traffic congestion; demonstrate government's commitment to public transport; increase Gauteng's economic growth; to create employment, to promote black economic empowerment (BEE); and promote the growth of small and medium-sized enterprises (SMMEs). Added to this, the Gautrain Project would contribute toward urban restructuring, link Tshwane to Johannesburg; uplift the Johannesburg and Tshwane central business districts; and link Johannesburg to the International Airport. The Gautrain Project could also be a catalyst to generate new resources for the promotion of public transport. Mr Van Der Merwe highlighted that the Tshwane, Johannesburg and Ekurhuleni municipalities officially supported the Project.

Mr Van Der Merwe provided an overview of the Gautrain's proposed system. The Gautrain would run on an international standard gauge line and would be capable of reaching 180 km/h. It was estimated that there would be 134 000 passenger trips on the Gautrain per day. Most of these passengers would be people that were currently using motor vehicles to travel to and from work. In order to attract these people, ample park and ride facilities would be constructed. Approximately 250 buses would be commissioned to shuttle these people from the parking facilities to the Gautrain stations. Added to this, international tourists and business people would be the target market for Gautrain running between Rosebank and the Johannesburg International Airport. Mr Van Der Merwe added that the Gautrain would have a positive impact on the province's economy. Approximately 130 000 permanent and temporary jobs would be created. It was estimated that the Gautrain would increase Gauteng's gross domestic product by approximately one percent.

Mr Van Der Merwe noted that the cost of the Gautrain Project had initially been estimated at R 7 billion. However, there had been various cost increases, which had occurred due to Environmental Impact Assessment (EIA) requirements, the rising cost of property, and the inclusion of VAT into the construction elements. In 2002, the estimated cost had risen to R 12 billion. Recently, the Minister of Finance had estimated that it would cost government R 20 billion to develop the Gautrain over a five-year period. However, it was unlikely that the estimated cost would not rise any further, as the contract with the preferred bidder would be a fixed price lump sum contract. Mr Van Der Merwe then discussed the affordability of the Gautrain. It was noted that the Gauteng government would have to borrow funds for the Gautrain. The Minister of Finance had agreed to this in principle. Added to this, the Department of Transport's Cabinet memo had been approved in principle. Mr Van Der Merwe added that the Gautrain formed an integral part of South Africa's 2010 World Cup bid. The International Federation of Football Federations (FIFA) had recommended that the Gautrain form the backbone of the Gauteng public transport system for the World Cup.

Mr Van Der Merwe outlined the Gautrain Project's funding details. Public sector funding for the Project's capital cost would be garnered from three sources, which were from the Gauteng Province's budget; Provincial borrowing from the national government; and a conditional grant from the National Treasury via the National Department of Transport. The private sector would be investing approximately R 3.9 billion in capital costs; however, they would be undertaking operational risk.

Mr Van Der Merwe highlighted that the Gautrain was incorporated into certain sections of the Provisional Land Transport Framework (PLTF). Indeed, it was also aligned with the Gauteng Spatial Development Framework; the Gauteng Transport Strategy; the Gauteng Strategic Public Transport Network; and the Gauteng Integrated Land-use and Transport Framework; the affected municipalities' Integrated Transport Plans; the affected municipalities' Integrated Development Plans; and the Airport Company's plans. A Public Transport Integration Task Team had also been established to investigate how the Gautrain could be integrated within strategic land-use and transport interventions.

Mr Van Der Merwe noted that negotiations were underway with Bombela Consortium to finalise the concession agreement. It was hoped that construction on the Project would begin in early 2006. The construction period would be approximately 54 months. As a result, it was hoped that the entire Gautrain system would be operational by April/May 2010.

Question:

You have been assigned by Mr Van Der Merwe to assist him with implementing risk management on the project. He tells you that he is really concerned about the project budget and he is not sure how much it will cost to complete the project. He asks you for your suggestion. As an experienced Risk Management Professional, what recommendations will you suggest to Mr Van Der Merwe and justify your response.

Reference no: EM133251228

Questions Cloud

What recommendations will you suggest to mr van der merwe : What recommendations will you suggest to Mr Van Der Merwe and justify your response - how the Gautrain could be integrated within strategic land-use
Secondary prevention program : Which of the following is an example of a secondary prevention program?
Hormone responsible for glucose release between meals : Their physician thinks they have a mutation in the hormone responsible for glucose release between meals.
What is type of wave to research : What is one type of wave to research and ow it impacts our lives, and if these impacts are positive or negative?
How much it will cost to complete the project : How much it will cost to complete the project. He asks you for your suggestion. As an experienced Risk Management Professional, what recommendations
What challenges and opportunities do you see for companies : BA 437 Bellevue University business to foreign markets as well. What challenges and opportunities do you see for these companies as they expand into foreign
What factors influence effective communication in workplace : What factors influence effective communication in the workplace? What factors hinder effective communication in the workplace
Making small acidic molecules : What is the medical condition called when people consume very little carbohydrates and the body switches to making small acidic molecules from fat to feed brain
What is wrong with helen diet : For many college students, their freshman year is the first time they are making all their own food choices, and they don't always make the best ones

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd