Reference no: EM132829345
Question - On January 2, 2020, Dalampasigan Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows:
January 2, 2020 P200,000
September 1, 2020 600,000
December 31, 2020 600,000
March 31, 2021 600,000
September 30, 2021 400,000
Dalampasigan borrowed P1,100,000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period. The company also had P4,000,000 in 9% bonds outstanding in 2020 and 2021.
Required - How much is the value of the plant at completion?