Standard Faucets uses standard costing and recorded the following data for the month of August:

Standard direct labor rate                              $10.00 per hour
Standard hours allowed for actual production     20,000 hours
Actual direct labor rate                                  $10.50 per hour
Labor efficiency variance                           $5,000 favorable

Question 1: How much is the labor rate variance for August?

Option 1: $0

Option 2: $14,750 unfavorable

Option 3:  $9,750 unfavorable

Option 4: $4,750 unfavorable

Reference no: EM132528738

Questions Cloud

Discussion of the various controversies : This forum is for discussion of the various "controversies" that surround evolution. Should there really be any controversy?
What is meant by the wobble position in a codon : What is meant by the "wobble position" in a codon/anti-codon and what are its implications for silent and non-silent mutations?
How many staplers must marks produce in july : The company plans to have 15% of the next month's sales in inventory at the end of each month. How many staplers must Marks produce in July?
Chordates in our phylogeny : Tunicates lack vertebrae, a trait present in all other chordates in our phylogeny. Would it be correct to refer to tunicates living today as "basal," "ancestral
How much is the labor rate variance for august : How much is the labor rate variance for August? Standard Faucets uses standard costing and recorded the data for the month of August
Describe two communication techniques : 1. Which age group discussed in chapter 5 have you communicated with the most.
Why makes sense based in the function of estrogen : How does the increase in the estrogen level correspond to the thickness of the uterine lining (endometrium)? Explain why this makes sense based in the function
What is the best characterization of the challenges : What is the best characterization of the challenges for each, based on your investigations in this lab?
How much is total accounts receivable at the end of august : How much is total Accounts Receivable at the end of August? Green Company's sales are 20% cash and 80% credit. Of the credit sales, 60% are collected

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd