Reference no: EM132485338
Marks Construction is experienced in bidding on long-term construction projects of this type, with the typical project lasting from 15 to 24 months. Marks uses the percentage-of-completion method. Progress toward completion is measured on a cost-to-cost basis. Marks began work on a contract at the beginning of 2019.
Data for 2019 follow:
Contract price $2,000,000
Estimated costs
Labour $425,000
Materials and subcontracts 875,000
Indirect Costs 200,000
1,500,000
Estimated gross profit $500,000
At the end of 2019, the following was the actual status of the contract:
Progress Billings to date $1,115,000
Costs incurred to date
Labour $207,000
Materials & subcontracts 519,000
Indirect costs 75,000 801,000
Latest forecast of total costs 1,500,000
Point 1: It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored onthe job site, but not yet installed, costing of $51,000. Thesecosts should not be considered in the costs incurred to date.
Instructions
Question 1: Calculate the percentage of completion on the contract at the end of 2019.
Question 2: Calculate the gross profit that would be reported on this contract for 2019.
Question 3: Prepare the journal entry to record the revenue and gross profit for 2019 on Mark's books.
Question 4: Indicate the account(s) and the ammount(s) that would be shown on Mark's statement of financial position. Cash collected during the year was $980,000.
Question 5: Assume, instead of $1,500,000, the latest forecast of total costs at the end of 2019 was $2,050,000. How much income (loss) would Mark the report for the year 2019?