Cooper uses the percentage-of-completion method and began work in 2018 on a contract for $8,000,000. Other data are as follows:
2018 2019
Costs Incurred to Date $3,600,000 $5,100,000
Estimated Costs to Complete $2,400,000
Billings to Date $2,800,000 $8,400,000
Collections to Date $2,000,000 $7,200,000
Problem (a) How much revenue should be reported for 2018? Show your computation.
Problem (b) Make the entry to record progress billings during 2018.
Problem (c) Make the entry to record the revenue and gross profit for 2018.
Problem (d) How much gross profit should be reported for 2019? Show your computation.