How much authority a project manager will possess on project

Assignment Help Business Management
Reference no: EM131294539

Question

1. In a strong matrix structure, employees take daily direction from:
Project manager only
Both, but the project manager has greater influence
Both, but the functional manager has greater influence
Functional manager only

2. If the schedule variance is positive and the cost variance is negative, the project's status is:
Over budget and behind schedule
Under budget and ahead of schedule
Over budget and ahead of schedule
Under budget and behind schedule

3. Which category of projects would involve a large number of functional units where the workers may be assigned either part-time or full-time?
Special
Individual
Staff
Matrixed

4. Which type of chart provides the least "predictive" value?
PDM
ADM
PERT
Bar chart

5. Scope creep is generally the result of:
Too much detail in the specifications
Having too many levels in the WBS
Poorly defined SOW
Having the wrong people assigned to the project

6. Which of the following is the role of the PM rather than the role of the functional manager?
Where it will be done
How the work will be done
Who will do it
What work will be done

7. The balance between quality and cost is called:
Produceability
Salability
Availability
Operability

8. The EVMS term that represents the value of work actually accomplished is:
BAC
AC
EV
PV

9. Which of the following would be the first item to be discussed in the initial kickoff meeting for a project?
Understanding of the budget
Understanding of the schedule
Understanding of the requirements
Understanding of the plan

10. Quality is defined by the:
Project team
customer
Project manager
Project sponsor

11. Which of the following people has the greatest influence on how much authority a project manager will possess on a given project?
The project sponsor
The customer
The project manager's line manager
The project manager himself / herself

12. A project manager desires a work breakdown structure that goes through 6 levels of detail. Level 3 through level 6 would most likely be prepared by:
Customer
Subject matter experts
Project manager
Project sponsor

13. In which project life cycle phase does quality begin?
Initiation / planning
Monitoring & control
Closure
Implementation

14. Project management restructuring allowed companies to manage projects that _____.
Had undefined objectives
Could not be handled by the traditional organization
Did not require effective cost control
Require little functional integration

15. Risk constitutes a lack of knowledge _____.
Of future events
About the estimates
About the customer's requirements
About the environment

16. The two primary components of a risk are:
The probability and the impact
The impact and the event
The impact and the amount at stake
The event and the probability

17. Which of the following standard project estimating techniques is usually accomplished in weeks?
Engineering
Parametric
Analogy
Grassroots

18. The hardest part in creating a best practices library is:
Storage
Classification
Evaluation
Knowledge transfer

19. A typical project office (not to be confused with a project management office) responsible for the management of a large project includes the project manager and the:
Project sponsor and assistant project managers
Assistant project managers
Assistant project managers and functional managers
Project sponsor

20. Industries that have _____ tasks and operate in a _____ environment demonstrated the greatest need for project management.
Complex; Dynamic
Simple; Static
Complex; Static
Simple; Dynamic

21. Pricing out the construction cost of a home by a cost per square foot would be representative of a(n) _____ estimate.
Grassroots
Parametric
Engineering
Analogy

22. The collective term for the formal quality activities and processes is called:
Quality control
Quality visions
Quality assurance
Quality policies

23. The difference between the cost baseline and the contracted cost is the:
Profit
Management reserve
Cost of scope changes
Cost at completion

24. Plans such as the cost plan, schedule plan and quality plan are referred to as:
Subsidiary plans
Specialized plans
Integration plans
Functional plans

25. Companies can become reasonably mature in project management by designing the right support systems. In general, how much time usually elapses after maturity before a company becomes excellent in project management execution?
2 years
1 year
5 years
10 years

26. The best source of revenue for a customer-requested scope change is:
A customer-funded contract amendment
Profits
Management reserve
Undistributed budget

27. During the 1970s and 1980s, formal project management practices were put in place because the constraints were _____ and _____ boundaries had to be crossed
Tight; few
Tight; several
Loose; few
Loose; several

28. A charting technique designed to illustrate the inductive and deductive reasoning necessary to achieve some objective is called a _____ Diagram / network
Descriptive
Intuition
Gantt
Logic

29. Which of the following is often overlooked when planning and budgeting a project?
Customer's milestones
Timing of the deliverables
Number of meetings with the customer
Cost and size of contractual documentation

30. What is the project sponsor's responsibility with regard to the WBS preparation?
The sponsor should not be involved in WBS development.
Make sure all work packages are well-defined.
Make sure that the management levels of the WBS are correct.
Make sure that the technical levels of the WBS are correct.

Reference no: EM131294539

Questions Cloud

Describe the external environment to the organization : Describe the External Environment to the organization showing its impact and the behavior of the manager to mitigate or avoid it.
Diluted earnings per share : On January 1, 2014, Crocker Company issued 10-year, $3,660,000 face value, 6% bonds, at par. Each $1,000 bond is convertible into 22 shares of Crocker common stock. Crocker’s net income in 2014 was $252,000, and its tax rate was 45%. Compute diluted ..
Comment and substantiate answer with examples : Multinational corporations have their headquarters in one country but operate in many countries." Comment and substantiate your answer with examples.
Executive director of a long-term care facility : The Midterm Exam is an applied case study scenario where you are the executive director of a long-term care facility that has decided to pursue Joint Commission accreditation.
How much authority a project manager will possess on project : Which of the following people has the greatest influence on how much authority a project manager will possess on a given project? Which of the following standard project estimating techniques is usually accomplished in weeks?
Parity system to a merit system : How do you think employees might react to a change from a parity system to a merit system? How about a change from a merit system to a parity system?
Bond retirement : (Bond Retirement) Simply Lemonade had outstanding $5 million of 11% bonds (interest payable July 31 and January 31) due in 10 years. On July 1, it issued $7 million of 10% 15-year bonds (interest payable July 1 and January 1) at 98. A portion of the ..
Bond issued at discount : (Bond issued at discount) Naked Juice issues $600,000 of 7% bonds, due in 10 years on January 1, 2013. The bonds were issued for $559,224, and pay interest each July 1 and January 1. Naked Juice uses the effective-interest method. Prepare the company..
Bond issued at face value : (Bond issued at face value) Green Tea issued $300,000 of 10% bonds on January 1, 2015. The bonds are due January 1, 2020, with interest payable each July 1 and January 1. The bonds are issued at face value. Prepare Green Tea’s journal entries for (a)..

Reviews

Write a Review

Business Management Questions & Answers

  Conduct research in order to contrast agency theory

For this essay, you will conduct research in order to contrast agency theory and stewardship theory in corporate governance. In your essay, be sure to address the following comments:

  Calculate daisy gross salary per month

(a) Write the ratio of their investments in its simplest terms (b) Calculate how much each partner received in total for the first 6 months of trading. Before payment of Daisy's net salary, deductions had been made totalling 18% of her gross salar..

  How companies are reacting to the laws or regulations

The legal or regulatory frameworks affecting marketing are at different stages around the world; different priorities and influences are at work. Explain their impact on marketing in your country and how companies are reacting to the laws or regul..

  How many workers will be needed to man the line

If demand for televisions is reduced to 100 sets per 40-hour week, how many workers will be needed to man the line? Re-balance the line and re-calculate its efficiency.

  Damage to established ideas which lurks in relationship

is dangerous because most economists would sense "the damage to established ideas which lurks in these relationships." Examine what he means by this.

  Discuss different methods for cost effective evaluations

show and provide examples of cost effectiveness evaluation, cost/benefit evaluation, cost saving analysis, and utility analysis for methods of evaluating the costs of training for the organization.

  Discussion segmentation

Discussion Segmentation

  Organizational change- how companies fail

Organizational change is not always successful and find factors that can cause change initiatives to fail and the five pillars that can cause them to succeed.

  Decision making in the strategic planning process

How is data based decision making utilized in the strategic planning process?

  How would you go about making given decision

Suppose that you. as founder of a business.- How would you go about making this decision? Would you pro-mote your son?

  Evaluate the organization vision statement

Create a 12- to 15-slide Microsoft PowerPoint presentation for a Mini-Strategy using the Mini-Strategy Outline. Include the following in your outline: Evaluate the organization's vision statement. Discuss the organization's current goals and object..

  Great fear of quantitative easing

1) Why did Britain, the USA, Japan, the European Monetary Union and others embark on it in early 2009 but not Australia? 2) What is the one great fear of quantitative easing? You must use the quantity equation to support your argument.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd