THE ESTIMATING PROBLEM

Barbara just received the good news: She was assigned as the project manager for a project that her company won as part of competitive bidding. Whenever a request for proposal (RFP) comes into Barbara's company, a committee composed mainly of senior managers reviews the RFP. If the decision is made to bid on the job, the RFP is turned over to the Proposal Department. Part of the Proposal Department is an estimating group that is responsible for estimating all work. If the estimating group has no previous history concerning some of the deliverables or work packages and is unsure about the time and cost for the work, the estimating team will then ask the functional managers for assistance with estimating.

Project managers like Barbara do not often participate in the bidding process. Usually, their first knowledge about the project comes after the contract is awarded to their company and they are assigned as the project manager. Some project managers are highly optimistic and trust the estimates that were submitted in the bid implicitly unless, of course, a 989 significant span of time has elapsed between the date of submittal of the proposal and the final contract award date. Barbara, however, is somewhat pessimistic. She believes that accepting the estimates as they were submitted in the proposal is like playing Russian roulette. As such, Barbara prefers to review the estimates.

One of the most critical work packages in the project was estimated at twelve weeks using one grade 7 employee full time. Barbara had performed this task on previous projects and it required one person full time for fourteen weeks. Barbara asked the estimating group how they arrived at this estimate. The estimating group responded that they used the three-point estimate where the optimistic time was four weeks, the most likely time was thirteen weeks, and the pessimistic time was sixteen weeks.

Barbara believed that the three-point estimate was way off of the mark. The only way that this work package could ever be completed in four weeks would be for a very small project nowhere near the complexity of Barbara's project. Therefore, the estimating group was not considering any complexity factors when using the three-point estimate. Had the estimating group used the triangular distribution where each of the three estimates had an equal likelihood of occurrence, the final estimate would have been thirteen weeks. This was closer to the fourteen weeks that Barbara thought the work package would take. While a difference of 1 week seems small, it could have a serious impact on Barbara's project and incur penalties for late delivery.

Barbara was now still confused and decided to talk to Peter, the employee that was assigned to do this task. Barbara had worked with Peter on previous projects. Peter was a grade 9 employee and considered to be an expert in this work package. As part of the discussions with Barbara, Peter made the following comments:

I have seen estimating data bases that include this type of work package and they all estimate the work package at about 14 weeks. I do not understand why our estimating group prefers to use the three point estimate.

"Does the typical data base account for project complexity when considering the estimates?" asked Barbara. Peter responded:

Some data bases have techniques for considering complexity, but mostly they just assume an average complexity level. When complexity is important, as it is in our project, analogy estimating would be better. Using analogy estimating and comparing the complexity of the work package on this project to the similar works packages I have completed, I would say that 16-17 weeks is closer to reality, and let's hope I do not get removed from the project to put out a fire somewhere else in the company. That would be terrible. It is impossible for me to get it done in 12 weeks. And adding more people to this work package will not shorten the schedule. It may even make it worse.

Barbara then asked Peter one more question:

Peter, you are a grade 9 and considered as the subject matter expert. If a grade 7 had been assigned, as the estimating group had said, how long would it have taken the grade 7 to do the job?

"Probably about 20 weeks or so," responded Peter.

QUESTIONS

1. How many different estimating techniques were discussed in the case?

2. If each estimate is different, how does a project manager decide that one estimate is better than another?

3. If you were the project manager, which estimate would you use?

Read the above paragraph and answer the below Questions in APA Format with Minimum of 125 words for each question.

Reference no: EM132274341

Questions Cloud

What can human resources do to help : What can human resources do to help make their companies competitive (what can they do to make company better than others
Write analysis of many different types of data : Dudley (2009) points out that social work practice is usually embedded in programs. While you looked at practice evaluation using single-subject design.
Describe the pathophysiological mechanisms of chronic asthma : Describe the pathophysiological mechanisms of chronic asthma and acute asthma exacerbation. Be sure to explain the changes in the arterial blood gas patterns
Explain leaders role in improving organizational : Explain leaders role in improving organizational effectiveness (how do leaders make organizations better)
How many different estimating techniques were discussed : "Does the typical data base account for project complexity when considering the estimates?" asked Barbara.
Growing demand for more ethically responsible : How much do you agree that business must acknowledge society's existence and society's growing demand for more ethically responsible business practice?
Business ethics and corporate social responsibility : Explain the link between Values, Business Ethics and Corporate Social Responsibility?
Partner company has offered one of your employees : What if you have found that a partner company has offered one of your employees a bribe not to tell your company about something unethical
What is the link between the job characteristics model : What is the link between the Job Characteristics model and EACH of the following components of the HRM system - Job Analysis, Selection, Training & Development

Reviews

Write a Review

Operation Management Questions & Answers

  What is the basic building block of structure

What is the basic building block of structure? What are the advantages and disadvantages of each?

  What if the clause was only limited to tenants of color

What if the clause was only limited to tenants of color? Would that have additional effects on a court’s ability to render it unenforceable?

  Ship organizational behavior in action

Carnival Corp. CEO Arnold Donald Works at Righting the Ship ORGANIZATIONAL BEHAVIOR IN ACTION

  Evaluate the success of the implementation of the plan

Include specific metrics that will be used to evaluate the success of the implementation of the plan.

  Distinctive competencies play in strategic management

What are your thoughts regarding the roles resources, capabilities and the concept of Distinctive Competencies play in strategic management?

  What is the average unit cost of the order

Suppose Company X decides to buy 8,000 units from Supplier A. What is the average unit cost of the order?

  Determine the utilization and the efficiency

Would you say that systems that have higher efficiency ratios than other systems will always have higher utilization ratios than those other systems? This is not necessarily . If the design capacity is relatively , the utilization could be even th..

  What is the repair shops capacity utilization

A fleet repair facility has the capacity to repair 500 trucks per month. However, due to scheduled maintenance of their equipment, management feels that they can repair no more than 450 trucks per month. Last month, two of the employees were absent s..

  Nikita heads the human resource (hr) team

Nikita heads the human resource (HR) team at Strait Corp., a marketing firm. She has knowledge about how the firm earns revenues, about its clients and their requirements, and why the clients rely on the firm's services. This scenario illustrates Nik..

  Analyzing the competitive dynamics of the industry

It is necessary to grasp and understand the industry’s general economic characteristics by analyzing the competitive dynamics of the industry.

  China limits exports of rare earth materials closing case

Rare earth metals are a set of 17 chemical elements in the periodic table and include scandium, yttrium, cerium, and lanthanum. Small concentrations of these metals are a crucial ingredient in the manufacture of a wide range of high-technology produc..

  Difference between traditional tax and audit services

As the rate of innovation increases, companies face expanding product/service lines, shorter product and service lifecycles, and more frequent product.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd