A senior MIS design class project team has developed the following schedule of activities for their project, using their best estimate of completion times. Both written and oral reports are required. Draw the project network. Can they complete the project in the 38 class days remaining until the end of the semester? Identify the critical activities. Identify the non-critical activities and their relevant slack times
Activity Immediate Activity TimePredecessorsA --- 3B --- 5C A, B 2D C 6E C 5F E 3G C 4H D, G, F 3I D, F 4J H 2K I, J 2
(a) Draw a project network for the above activities.(b) Determine which activities are critical(c) Determine which activities are non-critical and their respective slack times.(d) How long will the project take to accomplish?
desires to control inventory levels so as to minimize the sum of holding and order costs. It costs the firm $20 to place an order. Nike estimates its yearly inventory carrying costs
The tennis club has a number of inventories it must manage and must minimize all its expenses to stay in business. For each inventor, describe a goo management policy or system:
what issues would a judge decide? What if the person(s) with liability here doesn't have the money to pay Veronica's damages?
A distributor has heard that one of the major manufacturers from which it buys is considering going direct to the consumer
Elucidate how a race condition is possible also illustrate what might be done to prevent race condition from occurring.
The new-accounts office at the Savings and Loans Bank enrolls all new customers in checking accounts. During the three-week period in September encompassing the beginning of the new school year at State University
Which of three workstations, W, X, or Y, has highest aggregate workload, also thus serves as bottleneck for CKC.
Discuss whether or not your organization has optimized these organizational resources for effectiveness also efficiency. Justify your position. Illustrate what quality control improvement tool distinguishes between the important few also trivial ma..
The service level is the probability that the amount of inventory on hand during the lead time is sufficient to meet expected demand.
Value management (VM) is the application of value methodologies with the purpose of improving organizational effectiveness
Compute the multifactor productivity before and after purchasing the new equipment. Use labour cost and overhead cost to derive multifactor productivity.
The use of computers and JIT (Just-In-Time) inventory strategies has enabled SCM (Supply Chain Management) Systems to minimize WIP (Work-In-Process) inventories. Discuss this approach to Inventory control and ways to mitigate disruptions in the sup..
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd