Reference no: EM132738976
Geary Manufacturing has assembled the following data pertaining to two popular products.
Blender Electric mixer
Direct materials P 6 P 11
Direct labor 4 9
Factory overhead @ P16 per hour 16 32
Cost if purchased from an
outside supplier 20 38
Annual demand (units) 20,000 28,000
Plroblem 1: Past experience has shown that the fixed manufacturing overhead component included in the cost per machine hour averages P10. Geary has a policy of filling all sales orders, even if it means purchasing units from outside suppliers. If 50,000 machine hours are available, and Geary Manufacturing desires to follow an optimal strategy, it should
A. produce 25,000 electric mixers, and purchase all other units as needed
B. produce 20,000 blenders and 15,000 electric mixers, and purchase all other units as needed
C. produce 20,000 blenders and purchase all other units as needed
D. purchase all units as needed