How Gantt Charts Can Help Avoid Disaster
By Linda Russell
Having run 15 months late on completion of a construction project, a building company incurred extensive penalty charges, which eventually led to its closure. Not having any project Gantt charts indirectly led to the company's failure.
Background
In my article "Gantt Charts, Pert Charts: What Use are They?" I said that Gantt charts are useful tools to help you manage better, but they won't give you all the answers. What I didn't say is that not having a Gantt chart can be disastrous: a company recently went into receivership, partly because it didn't have Gantt charts showing the critical paths on a major construction project.
Penalty Charges
The original contract for the construction of a block of flats did not include a dated project plan showing the critical path. When changes to the specification were made by the customer, no plan revisions could be produced to show how these changes would affect the project end date. The flats were finally ready for handover some 15 months later than the original agreed end date, leading to penalty charges.
In order to contest the penalty charges, the company needed to show:
The handover date specified in the contract was possible within the original specification.
That the end date was bound to slip because of the extra tasks and extended durations caused by the customer's changes.
All they had was a series of spreadsheets listing the tasks undertaken: a new spreadsheet was created when each change was made. The spreadsheets didn't show the variances from the original plan, nor what the impact of those changes was on the project dates.
How Gantt Charts Would Have Helped
If they had created a Gantt chart at the contract stage, they would have had a baseline plan against which they could monitor their progress.
When the customer requested amendments to the specification, the company could have added in the necessary extra tasks and changed the durations of the existing tasks as required: this would have clearly shown the handover date slippage. The customer could then have been called upon to sign an amendment to contract, agreeing a revised end date.
Without these tools, the company was unable to prove that the delay was not caused by their own inefficiencies, although it could be argued that trying to manage a complex construction project without using appropriate planning tools is an indication of inefficiency in itself.
Conclusion
If you are called upon to manage a project for a customer where time is of the essence, you need to use appropriate tools to monitor the progress and work out the impact of changed circumstances, and communicate the changes to all concerned.
How would you have applied the project risks in addition to the Gantt Charts?
How would you have gone about implementing a practical approach to a risk management assuming your initial approach is to create a risk management plan?
Hint: Use tools and techniques, charts, diagrams, etc., as required, in your analysis.
Define the first step of research in your own words
: Write a one to two (1-2) page essay in which you: Identify the first step in the student's guide to research. Define the first step of research in your own words
|
Provide a criticism of a film
: An evaluative essay is a way of taking a thing or idea and explaining why it is of value. In 1-2 pages, provide a criticism of a film, television show, album, work of art, or piece of literature
|
Could free riders be victims
: Social loafing costs companies around the world millions of dollars every year, as a manager, how would you make sure that you have fully contributing members in your teams? Could "free riders" be victims, and can possibly be more productive if prope..
|
Determine how many sections to schedule
: The Chairperson of the Department of Business Administration at TSU wants to forecast the number of students who will enroll in Operations Management next semester in order to determine how many sections to schedule. Compute an exponentially smoothed..
|
How gantt charts can help avoid disaster
: Having run 15 months late on completion of a construction project, a building company incurred extensive penalty charges, which eventually led to its closure. Not having any project Gantt charts indirectly led to the company's failure. How would you ..
|
Discuss the problems encountered in implementing ideas
: Discuss the problems encountered in implementing ideas. How can they be overcome? What would you do if some of the problems could not be overcome?
|
About the goods versus services
: Fred and Zuma Palermo contacted Colorado Carpet Installation, Inc., for a price quotation on providing and installing new carpeting and tiling in their home. In response, Colorado Carpet submitted a written proposal to provide and install the carpe..
|
Some disadvantages to linear programming
: When discussing several disadvantages of linear programming; clearly explain the reasons for your choices. Some disadvantages to linear programming include the fact that usually all of the variables that need to be taken into account in order to solv..
|
Strategically about industry and competitive conditions
: Thinking strategically about industry and competitive conditions in a given industry involves evaluating such considerations as. how often sellers alter their prices, how sensitive buyers are to price differences among sellers, whether the item being..
|