Eight weeks ago Iceberg Limited opened its newly built food retail store on a prestige site it acquired at a premium price from Papete Investments Plc. It has invested a great deal in marketing its frozen food operations around the theme of ‘customer confidence’. The refrigerator system was manufactured and installed by Keep–it–Cold Limited for £250000, who also have the maintenance contract costed at 7.5% of the contract value per year – £18750 – (though for the next 12 months the equipment remains under warranty) with a 2 hour call-out commitment.

Keep–it–Cold is sited in a nearby city, 130 miles to the north of Iceberg's new store and it services clients up to a radius of 150 miles from its depot.

On Friday of last week at 2 p.m., the visual alarm on one of the refrigerated display cabinets in the delicatessen section became active, indicating that the temperature had risen slightly above the regulation 3 to 5 degrees range. A member of staff called Keep–it–Cold to request a visit by their service engineer. She agreed that the alarm was not of sufficient seriousness to require an immediate response and also agreed that the service visit could be postponed until the next day.

This suited Keep–it–Cold because that afternoon all of their service engineers had been assigned to calls to the north of their depot and were furthest away from Iceberg's store. When the store was opened by the deputy manager next morning at 8 a.m., he discovered that the entire refrigeration system for the whole store had gone down during the night and that all of the display cabinets and the storage rooms were close to room temperature. There was no way that any of the contents of the store could be saved and every unit had to be emptied and their contents disposed of in sealed bins. This represented a stock loss of £40000.

To compound the problem, the service engineer arrived at 11 a.m. instead of 8 a.m. when she was expected. She explained that she had been working up to 2 a.m. that morning on a major emergency 200 miles away. She had ‘signed on’ for duty at 9.00 a.m. and had gotten to Iceberg as fast as she could.

Meanwhile, at Iceberg, the deputy manager had been on the telephone several times to Keep it Cold, exhibiting various degrees of rage about what had happened on Friday and had become increasingly angry about the non-appearance of an engineer. He was told that on the basis of the conversation with his colleague on the previous day it had been agreed that the alarm did not indicate a major emergency and that they had not received any calls between 2 p.m. and when the store had closed at 8 p.m. to indicate that the alarm had gone from an initial indicator warning through the subsequent warning levels to ‘critical’. As far as they understood, the initial warning stage had remained static and they had no reason to revise their non-emergency grading of the problem.

The deputy manager stated that his member of staff did not have the authority to agree anything with Keep–it–Cold about service responses and that she had clearly been ‘persuaded’ (later described as ‘intimidated’) by whoever had answered her call to accept a lower and ‘wholly unacceptable’ response. His case was weakened by being unable to explain why she had not reported to him or another manager their response to her call. That week the Store Manager was on holiday and his deputy had taken his ‘half day’ that Friday afternoon.

When Iceberg's security monitoring service had rung Iceberg's Regional Office to report the initial alarm in one of the stores, they were told that Iceberg ‘was aware of the situation’ (because the employee had reported to them at 2.30 p.m. that she had requested a service call from Keep–it– Cold – though not, unfortunately that the engineer was not coming until the next day). They had received the same response when, throughout the night, their electronic 3 monitors picked up the 4 other alarms. Iceberg's Night Unit assumed that Keep–it–Cold engineers were on the premises dealing with the problem. They had not rung the store nor Keep–it–Cold to check their assumption.

The initial phone calls between Iceberg and Keep–it–Cold were argumentative and blame seeking.

Whatever had happened the previous day, Iceberg insisted that Keep–it–Cold's engineers should have been on their premises at 8 a.m. Keep–it–Cold insisted that they were in no way responsible as they were not informed of the worsening situation either by Iceberg's local staff, or its Regional Office, and they had no direct link to Iceberg's monitoring service.

Iceberg calculated that it had lost £56000 as a result (£40000 stock, £14000 net profit and £2000 in labour costs) on what would normally have been a busy week-end. This was apart from the inestimable damage to their reputation with their customers, especially as the store was brand new in the area and the equipment was only eight weeks old. They demanded compensation from Keep–it–Cold and warned them that their reputation was at risk too because, once this incident was reported to Iceberg's head office, it could put in jeopardy their maintenance contracts and their role as a major supplier of refrigeration equipment to the whole group (256 stores across the country, with one new store a month scheduled for the next two years).

How serious the implications were for Keep–it–Cold is a matter of conjecture but the business relationship was at risk to some extent. They had a good reputation generally but were convinced that they were not solely to blame and that the local store management had much to answer for because of their absence that afternoon, as did Iceberg's regional office for how they had responded to the calls from their monitoring service that night.

A meeting has been called to discuss the problem.

Answer all the below questions.

1. What is the main common interest of Iceberg and Keep–it–Cold in this dispute?

2. How far should Iceberg push for compensation?

3. Should Keep–it–Cold resist or pay compensation?

4. What proposal might Iceberg make to resolve the dispute?

5. What would jeopardize Iceberg's and Keep–it–Cold's chances of resolving the immediate problem?

Reference no: EM132097913

Questions Cloud

Modern electronic health record system : You work for a small community hospital that has recently updated its health record system to a modern electronic health record (EHR) system.
Detail the four functions of engineering management : Describe in detail the 4 functions of engineering management (Planning, Organizing, Leading, and Controlling)
What is the total annual cost of supplies : A community hospital in PA has a 15% supply expense ratio. If total operating expenses are $1 million this month, what is the total annual cost of supplies?
Have you been volunteered in an organisation : Have you been volunteered in an organisation? what are the ethical dilemma that you faced?
How far should iceberg push for compensation : What is the main common interest of Iceberg and Keep–it–Cold in this dispute? How far should Iceberg push for compensation?
What are the competing issues : What are the competing issues? Using the Grossman Model, what preliminary assumptions can be made?
Which kind of job evaluation is used for that position : Identify which kind of job evaluation is used for that position.
Focusing on the deresky supplement : What do you think they would need to know to successfully navigate our culture, both personally and professionally?
Are there any examples of colorful-vivid imagery or language : Style - Are there any examples of colorful, vivid imagery or language? Slogans? Symbols?

Reviews

Write a Review

Operation Management Questions & Answers

  Find out the optimal use of applichem plant capacity

Find out the optimal use of Applichem's plant capacity using the solver in excel. Illustrate what would you recommend that Applichem management do.

  Differential analysis-financial statements-capital budgeting

Making decisions as a manager using differential analysis, financial statements, and capital budgeting.

  How important is proofreading

How important is proofreading? In business how much damage can come from a lack of proofreading? As a manager how you can both become a stronger proofreader and stress the importance to your employees? Explain. Why or Why not? How?

  Principles of economics rather than evidence-based medicine

Discuss why the operation of the nation’s mental health system might be primarily based on principles of economics rather than evidence-based medicine.

  Develop and use emotional intelligence

Your natural leadership style is quite coercive. You are faced with an employee who is talented but has been underperforming.

  Associated with managing virtual teams

Identify at least two of the common problems that are associated with managing virtual teams. After identifying the problems, describe a team-building method that could be applied to each situation.

  Multiple regression analysis is broadly used in business

multiple regression analysis is widely used in business research in order to forecast and predict purposes. it is also

  Just attended pretrial conference for trial scheduled

Robert “Red” Newman, attorney-at-law, just attended a pretrial conference for a trial scheduled to begin next week. The case, Effingham v. Atwater, involves his client, Jessica Effingham. Judge Clarence Ginsburg strongly recommended that the plaintif..

  Influenced the treatment of disease and healthcare practice

Advances in technology have influenced the treatment of disease and healthcare practice. Choose one of the following hypothetical healthcare situations. Identify and describe how technological advances have influenced the way treatment and services a..

  Direct and indirect financial compensation

Explain the difference between direct financial compensation and indirect financial compensation.

  Management in action putting in the hours

Management in Action “Putting In The Hours” Discuss the following question: How would you respond if one of your employees wanted to come in early and get set up for their job but said they did not want to get paid for this extra time?

  Develop a compelling presentation to the operations manager

Develop a compelling presentation to the operations manager that will explore the benefits of implementing supply chain management on his floor.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd