How do schedule considerations add to your project risk

Assignment Help Operation Management
Reference no: EM13991368

Assume that you are the project manager for the construction of 10 conference facilities in your organization’s building in Florida. A statement of work has been given to you, and contracts have already been awarded. The project will require you to do the following for one of the conference facilities:

Install new electrical outlets and light fixtures: ABC Electrical Company (fixed price contract $20,500, week 1).

Install multimedia capability: Sound Masters, Inc. (fixed price contract $40,000, week 1 and $23,300, week 4).

Finish walls and apply custom paint color—Ocean Blue #4495: K&G Painters (cost reimbursable contract $24,990, week 2).

Install carpeting (color # 9984) and window shades (color # 5574): Best Flooring and Windows (fixed price contract $46,340, half in week 2 and half in week 3).

Install new furniture to match wall color (#4495), including 20 custom-made tables and 80 extra plush ergonomic chairs with wheels: Custom Furniture Experts, LLC (cost reimbursable contract $87,300, one quarter in week 1 and balance in week 4).

Install new furniture to match wall color (#4495), including 20 custom-made tables and 80 extra plush ergonomic chairs with wheels: Custom Furniture Experts, LLC (cost reimbursable contract $87,300, one quarter in week 1 and balance in week 4).

Complete inspection and acceptance within one month.

The 10 conference facilities will be worked on sequentially. Each conference facility is completed and ready for inspection before work can begin on the next facility. That means that your project is 10 months long and consists of 10 subprojects for each conference facility.

This is a high-visibility project, and the completion date is firm because your company is hosting a very important client meeting in the first conference facility in 45 days. The balance of the conference facilities have similar meetings already set up for their projected completion dates. Defaulting on the schedule is not an option.

You have a project team to help with the oversight and inspection of the project, which includes you and two technicians. Your salary is $1,050 per week and your technicians earn $13 per hour. You expect both of them to work 20 hours per week for the first three weeks and 40 hours in the last week of each conference facility subproject. However, one of your technicians may have surgery scheduled before the end of your first conference room subproject, which will result in you working additional hours. The decision on the surgery has not yet been made by his doctors. You will work 30 hours each week, without taking the potential employee absence into account. Your company overhead rate is 89% of labor and is not applied to vendor contracts. All materials are included in the vendor contracts. Artwork for a room this size could run between $10,000 and $15,000, depending on the quality of the frames. Your organization’s leaders want to impress their clients in this new facility, so you assume that the highest quality frames should be purchased.

Hurricane season just began, and you have seen reports of a major storm heading toward your town. You may have to evacuate, or worse yet, the facility could be damaged by the storm at the end of the first week of the first conference facility subproject. Evacuation would cause a one-week slip, and facility damage could cause a three-week slip, which would affect all the subsequent subprojects.

It is important that all contractors perform their work according to their contractual schedule. Any slip of one contractor will impact the next contractor’s beginning date.

Using this information, create a time-phased budget baseline on a spreadsheet. This baseline will consist of the incremental cost for each week, in addition to a cumulative cost for each week for 10 months.

Answer the following questions:

How do schedule considerations add to your project risk?

Which risks have the greatest potential to disrupt your project? Why?

Do you think you need contingency for this project? Why? How much?

What role do your risks play in your contingency estimate?

Submit the project baseline in an Excel spreadsheet.

Reference no: EM13991368

Questions Cloud

Do they focus on any specific demographics : Nuwave has now turned into a multibillion dollar company. Do they focus on any specific demographics? Do you think that they should ensure that more men/women know about this particular focus of their brand
Failing to warn flores of dangers of working with beehives : Negligence Curtis R. Wilhelm owned beehives and kept the hives on property he owned. John Black, who operated a honeybee business, contracted to purchase some beehives from Wilhelm. Black employed Santos Flores, Sr. to help him pick up the beehives f..
Express the number in decimal form : Express the number in decimal form (without exponents).4 (above & to right of 10)6.26 * 10
Do not use negative exponents in the answer : Simplify. Do not use negative exponents in the answer. Show work.-64y--------- =
How do schedule considerations add to your project risk : Assume that you are the project manager for the construction of 10 conference facilities in your organization’s building in Florida. A statement of work has been given to you, and contracts have already been awarded. Install new electrical outlets an..
Perform the indicated operation : Perform the indicated operation and simplify. Show work.9i * 9i
Deduct the advertising fee paid to grandson : Big Star wants to deduct the full $25,000 as a business expense. The grandson will report the $25,000 as income. Write a letter to Carla explaining whether Big Star can deduct the advertising fee paid to her grandson.
The other 8 is above the right of the b : Simplify.2 8 8 (ab ) (a b ) =The 2 is above and to the right of the b. the 8 is above the right of the a. The other 8 is above the right of the b.
Universalist perspective on human rights : Is a universalist perspective on human rights necessary for promoting health as a human right? Why or why not?

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd