How do find the net present value of the project

Assignment Help Managerial Accounting
Reference no: EM132598413

Boy-Boy , Incorporated , is considering the purchase of a machine that would cost R240,000 and would last for 5 years, at the end of which, the machine would have a salvage value of R48,000.

The machine would reduce labour and other costs by R62,000 per year.

Additional working capital of R7,000 would be needed immediately, all of which would be recovered at the end of five years. The company requires a minimum pretax return of 17% on all investment projects.

Question 1: Determine the net present value of the project. Show all your calculations.

Reference no: EM132598413

Questions Cloud

How does the membrane voltage potential change : Describe the changes that happen to the axon of a neuron after the threshold has been reached. What type of channels open and close?
How do calculate two factory overhead : How Calculate two factory overhead and three factory overhead variances. Chemical manufacturing company has budgeted capacity of 10000 direct labor hours
Explain your selection why you selected the topic : In this discussion you are going to conduct Online Research: Locate a Current Event, Article or Journal that describes one of the following.
What new cryptographic systems you are going to propose : Describe in detail what new cryptographic systems you are going to propose, how they work, and how they will enhance security. Be specific about these systems.
How do find the net present value of the project : Additional working capital of R7,000 would be needed immediately, Determine the net present value of the project. Show all your calculations.
Solution during glomerular reabsorption : In the process of glomerular filtration, water and smaller solutes are squeezed through a ball of capillaries called the glomerules
Describe what biometric security device : Describe what a biometric security device is and explain how your employer might use one to more of these devices to protect its servers.
What are the five ict enablers of energy efficiency : What are the five ICT enablers of energy efficiency identified by European strategic research Road map to ICT enabled Energy-Efficiency in Buildings.
Calculate maximum and minimum levels : From the book of records of Zaria Arts, it is found that the average daily, Calculate maximum and minimum levels, average maximum level and danger level.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd