ABC Mfg. Ltd. produces and sells a single product. Sales budget for the calendar year 2015 by quarter is as under:

Quarter       No. of units to be sold      Quarter    No. of units to be sold
Q.I                    22,000                         Q.III             15,000
Q.II                   28,000                        Q.IV               18,000

The year 2015 is expected to open with an inventory of 5,000 units of finished product and close with an inventory of 4,000 units.
Production is customarily scheduled to provide for two-thirds of the current quarter's sales demand plus one third of the following quarter's demand.

Problem 1: Compute the total number of units to be produced for the third quarter of year 2015

Reference no: EM132640179

Questions Cloud

What will the impact be on the break-even point : Flanders Manufacturing is considering purchasing, What will the impact be on the break-even point if Flanders purchases the new machinery?
Compute budgeted cash disbursement during august : Cash disbursements for other expenses are expected to be $12,200 for the month of August. Compute expected (budgeted) cash disbursement during August
Find marginal propensity to save : What would happen to the marginal propensity to save when a tax cut was enacted causing the multiplier to change to 5?
Calculate the change in saving : Consider the economy described in lecture 3 (a closed economy, the factors of produc- tion are in fixed supply and fully used
How do compute the total number of units to be produced : The year 2015 is expected to open with an inventory of 5,000 units. Compute the total number of units to be produced for the third quarter of year 2015
Explain the short-run impact : Explain the short-run impact of each of the following.
Find what were the firm budgeted collections for december : 20% are collected in the month of sale; 50% are collected in the first month after sale, what were the firm's budgeted collections for December?
Find aggregate supply curve : Use an aggregate supply-and-demand diagram to study what would happen to an economy in which the aggregate supply curve
Prepare a cost of goods manufactured schedule for clarkson : Prepare a cost of goods manufactured schedule. The data were taken from the records of Clarkson Company for the fiscal year ended June 30, 2020.

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd