How did these changes affect the sensitivity of the network

Assignment Help Project Management
Reference no: EM131113259

Question:

Prepare a memo that addresses the following questions:

1. Which if any of the resources are overallocated?

2. Assume that the project is time constrained and try to resolve any overallocalion problems by leveling within slack. What happens?

3. What is the impact of leveling within slack on the sensitivity of the network?

Include a Gantt chart with the schedule table after leveling within slack.

4. Assume the project is resource constrained and resolve any overallocation problems by leveling outside of slack. What happens? What are the managerial implications?

5. What options are available at this point in time?

Include a Gantt chart with the schedule table after leveling outside of slack.

Note: No splitting of activities is allowed.

Note: No partial assignments (e.g., 50 percent). All resources must be assigned 100 percent.

Part B

When you show the resource-constrained network to top management, they are visibly shaken. After some explanation and negotiation they make the following compromise with you:

- The project must be completed no later than February 2, 2012 (530 days).
- You may assign two additional development teams.
- If this does not suffice, you may hire other development teams from the out-side. Hire as few external teams as possible because they cost $50 more per hour than your inside development people.

Internal Development

Add as many development units (teams) as needed to stay within the 530 days. If you need more than two internal development units, then hire as few external teams as necessary. Select the cheapest possibility! Change as few activities as possible. It is recommended you keep work packages which require cooperation of several organizational units inside your company. You decide how best to do this.

Hint: Undo leveling prior to adding new resources.

Once you have obtained a schedule that meets the time and resource constraints, prepare a memo that addresses the following questions:

1. What changes did you make and why?

2. How long will the project take?

3. How did these changes affect the sensitivity of the network?

Include a Gantt chart with a schedule table presenting the new schedule.

Part 4

Based on the file created at the end of Part 3, prepare a memo that addresses the following questions:

1. How much will the project cost?

- After creating the resource pool, copy the screen image of Resource Sheet and paste into the Word document.

- After assigning resources, copy the screen image of the data entry screen and paste into the Word document.

- After time-constrained scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

- After resource-constrained scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

Part 3B

- After adding the two internal development teams and doing time-constrained resource scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources that over-allocated.

- After adding the two external development teams and doing time-constrained resource scheduling, copy the screen image of Resource Sheet and paste into the Word document. The Resource Sheet should show the resources are no longer over-allocated.

- After generating the Cashflow report, copy the screen image and paste in to the Word document. Change time scale to months.

- Answer all the questions given in Part 3 (five questions from Part 3A and three questions from Part 3B) and Part 4 (all questions). Submit your answers along with the screen shots as listed above as Appendices to the instructor through the Assignment tab on the Blackboard for evaluation.

In addition to the general instructions included in the Overview of this topic, you might find the following notes helpful in doing the Conveyor Belt homework.

Part 3A Notes

- Enter resource names from Table A2.12. For "Assembly/Test" enter "Assembly" for consistency with Table A2.11.
- Enter one team as 100% and two teams as 200% under Maximum Units.

Part 3B Notes

1. Add the two internal development teams for a total of four internal development teams to the resource pool. Level within the available slack (to complete the project within 530 days). If no resources are over-allocated, you have achieved your objective of completing the project in 530 days at the minimum cost. If any resources are still over-allocated, go to the next step.

2. Add the two external development teams as "DevelopmentX" to the resource pool. The external development teams are added as "DevelopmentX" since they are paid at a higher standard rate ($100 per hour). Identify the resources and the activities that are over-allocated through the Resource Usage view by scrolling horizontally. Make a note of the activities.

3. Select the shortest activity from the over-allocated activities from the previous step and change the resource assigned from Development to "DevelopmentX". Level within the available slack (to complete the project within 530 days). If no resources are over-allocated, you have achieved your objective of completing the project in 530 days at the minimum cost. Otherwise, identify the resources and the activities that are over-allocated through the Resource Usage view by scrolling horizontally. Make a note of the activities.

4. Repeat step the previous step until no resources are over-allocated, and you have achieved your objective of completing the project within 530 days at the minimum cost.

Verified Expert

The paper is about project management. Here, we have discussed about the usage of gantt chart, critical path and network diagram. Many calculation like EF, LF, ES, LS and slack are also discussed. The job is done in MS docx. This is a verified solution.

Reference no: EM131113259

Questions Cloud

Compute an estimate of the ending balance : Determine Ending Accounts Receivable your accounts receivable clerk, Mary Herman, to whom you pay a salary of $1,500 per month, has just purchased a new Buick.
What could be the main causes for these surpluses : In contrast to the United States, Japan has realized continuous current account surpluses. What could be the main causes for these surpluses? Is it desirable to have continuous current account surpluses?
The balance consists of the following : The balance consists of the following. Illustrate how the information above should be shown on the balance sheet of Patriot Company onDecember 31,2010.
Calculate the number of moles of gas added to the container : A flexible container at an initial volume of 8.15 L contains 9.51 mol of gas. More gas is then added to the container until it reaches a final volume of 15.1 L. Assuming the pressure and temperature of the gas remain constant, calculate the number of..
How did these changes affect the sensitivity of the network : Identify the resources and the activities that are over-allocated through the Resource Usage view by scrolling horizontally. Make a note of the activities.
Compute the full-load speed : At full load and rated voltage, the line current is 40 A, and the flux is 5% less than its no-load value because of armature reaction. Compute the full-load speed.
Pseudocode on the examples : A brief description of the task. The pseudocode associated with the task. Base the pseudocode on the examples provided in Chs. 4, 5, and 6 of Prelude to Programming.
Find the speed of the motor : If the machine is run as a motor while absorbing 10 kW from 230- V mains, find the speed of the motor. Neglect the brush-contact drop.
Write one ordered pair : 1. Write one ordered pair that is in the set AxB but is not in the set BxA., or explain why no such ordered pair exists. 2. Write one ordered pair that is in the set BxA but is not in the set AxB, or explain why no such ordered pair exists.

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd