Good condition for top-down estimating

Assignment Help Accounting Basics
Reference no: EM13916712

1) The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
A. About the same
B. About twice as much
C. About three times as much
D. About four times as much
E. About five times as much

2) Resource shortages, in the form of people, equipment, or materials, is a good example of
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

3) The accuracy of top-down estimates will typically be in the range of
A. Minus 50% to plus 50%
B. Minus 0% to plus 75%
C. Minus 20% to plus 60%
D. Minus 35% to plus 35%
E. Minus 10% to plus 30%

4) Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:
A. Hidden interaction costs
B. Things going wrong on a project
C. Normal conditions not applying
D. Changes in project scope
E. None of these are correct

5) In practice, estimating processes are frequently classified as
A. Top down/bottom up
B. Rough/polished
C. Precise/order of magnitude
D. Draft/final
E. Both A and B are correct

6) Which of the following is a good condition for top-down estimating?
A. Cost and time important
B. Fixed price contract
C. Customer wants details
D. Internal, small project
E. All of these are good conditions for top-down estimating

7) Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
A. Padding estimates
B. Planning horizon
C. Project structure
D. People
E. Organization culture

8) A/an _________ activity has more than one dependency arrow flowing from it.
A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

9) ________ activities are to be completed immediately following a particular activity.
A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

10) When translated into a project network, a work package will become
A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

11) Activities which can take place at the same time are termed
A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

12) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

13) The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:
A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

14) Which of the following is not one of the steps in the risk management process?
A. Risk response development
B. Risk assessment
C. Risk identification
D. Risk tracking
E. Risk response control

15) One of the keys to success in risk identification is
A. Critical thinking
B. Optimism
C. Pessimism
D. A "can do" attitude
E. All of these are correct

16) The 1999 NASA Mars Climate Orbiter is an example of
A. Disaster avoidance through proactive risk management
B. Murphy's Law
C. Proper use of critical thinking
D. Mismanaged risk control
E. Using historical records to assess risk

17) A list of questions that address traditional areas of uncertainty on a project is termed a risk
A. Risk profile
B. Questionnaire
C. Research
D. Query
E. Checklist

18) One common mistake made early in the risk identification process is to
A. Not all possibilities are considered
B. Participants are over-optimistic
C. Participants are over-pessimistic
D. Focus on objectives and not on the events that could produce consequences.
E. Too much attention is given to past events

19) In the beginning the focus of risk management should be on risks that
A. Impact the whole project
B. Impact the critical path
C. Are known
D. Have the greatest cost impact
E. Have the greatest schedule impact

20) More common problems associated with managing multiproject resources include all of the following except
A. Inefficient resource utilization
B. Delays in one project cause delays in other projects
C. Reducing "downtime" created by lack of tasks to perform
D. Resource bottlenecks
E. All of these are common problems

21) Which of the following is not one of the types of project constraints?
A. Physical
B. Technical
C. Resource
D. Time
E. All of these are types of project constraints

22) In a resource-constrained project, the first priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

23) . If resources are not adequate to meet peak demands, the resulting reschedule is termed
A. Resource-constrained scheduling
B. Time-constrained scheduling
C. Mandatory leveling
D. Project resource adjustment
E. Allocation

24) Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a _________ constraint.
A. Physical
B. Technical
C. Resource
D. Scheduling
E. Time

25) . In a resource-constrained project the third priority in assigning resources is usually given to activities with the
A. Smallest duration
B. Least slack
C. Most slack
D. Lowest identification number
E. Highest cost

Reference no: EM13916712

Questions Cloud

Disclose the extent of non-recurring revenue : Explain specifically why Qwest's failure to disclose the extent of non-recurring revenue violated the full disclosure principle in this situation.
What is error variance and how is it calculated : Q1. What is an F-ratio? Define all the technical terms in your answer. Q2. What is error variance and how is it calculated?
A separatory funnel and explain : Explain how use of 3 M HCl(aq) could separate it from the other components. To do so: show how acid would change the molecule; identify the phase in which this new species would be isolated in a separatory funnel and explain why it would be found the..
What is the probability that her partner will be selected : What's the probability that the attorney will be selected for the next case, assuming all registered attorneys are eligible? What is the probability that her partner will be selected in this scenario? What is the probability that the attorney OR her ..
Good condition for top-down estimating : The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
Check out writeaway hotels simulation at your student site : Check out the Writeaway Hotels simulation at your student site. If your instructor directs, follow the instructions to participate.
The ratio of numbers of mole of kmno4 : The ratio of numbers of mole of kmno4 and k2cr2o7 required to oxidised 0.1 mole sn2+ and sn4+ in acidic medium
Multiple independent-multiple levels of independent variable : Explain the difference between multiple independent variables and multiple levels of independent variables. Which is better?
How competitive advantage impact and influences organization : Describe how competitive advantage impacts and influences an organization or strategic group when referring to strategic management.

Reviews

Write a Review

Accounting Basics Questions & Answers

  How much control does fed have over this longer real rate

Hubbard argues that the Fed can control the Fed funds rate, but the interest rate that is important for the economy is a longer-term real rate of interest.   How much control does the Fed have over this longer real rate?

  Coures:- fundamental accounting principles

Coures:- Fundamental Accounting Principles: - Explain the goals and uses of special journals.

  Accounting problems

Accounting problems,  Draw a detailed timeline incorporating the dividends, calculate    the exact Payback Period  b)   the discounted Payback Period. the IRR,  the NPV, the Profitability Index.

  Write a report on internal controls

Write a report on Internal Controls

  Prepare the bank reconciliation for company

Prepare the bank reconciliation for company.

  Cost-benefit analysis

Create a cost-benefit analysis to evaluate the project

  Theory of interest

Theory of Interest: NPV, IRR, Nominal and Real, Amortization, Sinking Fund, TWRR, DWRR

  Liquidity and profitability

Distinguish between liquidity and profitability.

  What is the expected risk premium on the portfolio

Your Corp, Inc. has a corporate tax rate of 35%. Please calculate their after tax cost of debt expressed as a percentage. Your Corp, Inc. has several outstanding bond issues all of which require semiannual interest payments.

  Simple interest and compound interest

Simple Interest, Compound interest, discount rate, force of interest, AV, PV

  Capm and venture capital

CAPM and Venture Capital

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd