Review the Scenario detailed below. ODHS selected the Worldview Globalcom product for implementation in the E-mail Upgrade Project.

1. The project was accomplished in 14,960 hours versus the planned 12,000 hours, at a total cost of 1.56M versus the planned 1.25M over a ten month (versus nine month planned) schedule.

2. The Worldview vendor team had five key deliverables in the project, one of which was delivered 30 days late and another 10 days early.

3. The Ohio Department of Corrections, as a result of watching this effort, is deploying the Globalcom product for their organization.

4. Users report that they are very happy with the new e-mail system.

5. Mahoning County's infrastructure was too old to support the new e-mail system; they are being migrated next month as a separate project.

6. The Worldview contract was completed within established cost.

7. The Globalcom product's spam filter requires a different network configuration than is currently in place for the network.

8. The project team suffered from a 20% turnover rate during the life of this project, and exit interviews reveal salary was the overall cause.

Develop a Lessons Learned document for the Worldview project with these specific action items:

Write three project success criteria that would have been included in the charter-. Explain your criteria.

Using the addenda items detailed above in addition to information you creatively develop, write your lessons learned based on the criteria and the three components of cost, schedule, and performance (you may use these as individual sections of your paper). Note, not all the addenda items may even be pertinent.

Answer the following in a summarizing, final page: Was the project a success? Why or why not? If not, were portions of the project a success, and what was the impact of those success areas on the overall determination of project success?

Reference no: EM1343471

Questions Cloud

Effective study technique : Discussing concepts with others as a way of learning a concept would be an effective study technique for which of the following learning modalities?
Explain role of project management in modern organization : Before you plunge in to this project, take some time to reflect on most recent project on which you worked. What was your role? How many people were on it? What was produced? How long did it last
In the short story "gryphon : In the short story "Gryphon," what does the narrator's attitude toward Miss Ferenczi reveal about his own character?
Locating the position of hub : Map coordinates and the shipping loads for a set for a set of cities that we wish to connect through a central hub
Globalcom products spam filter : The Globalcom product's spam filter requires a different network configuration than is currently in place for the network
Develop a pac chart, interactivity chart : Develop a solution that will calculate the price of an item for each of the five days, given the original price. Test the solution for an item costing $10.00. Develop a PAC Chart, Interactivity Chart,IPO chart, Algorithm, and Flowchart
Soda vending machine design : Soda Vending Machine Design,    A state diagram showing the implementation of your design. Clearly show all the states and the conditions on which transitions occur.
Calculate the after-tax cost of debt : Solve the following problems and be able to discuss them relative to the financial management of a company.Calculate the after-tax cost of debt
Sleep cycles and the effects of sleep deprivation : Research topic:  Sleep Cycles and The Effects of Sleep Deprivation,  Submit the final product – your Research Paper  ,  The effects of sleep deprivation in humans: topography electroencephalogram changes in non- rapid eye movement (NRM) sleep vers..

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd