Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Determine the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Find what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM13363203

Questions Cloud

Given the following information for a one-year project : given the following information for a one-year project answer the following questions recall that pv is the planned
Difference between it project managers and traditional : difference between it project managers and traditional project managers.all projects are constrained by three factors
Emotional intelligence importance for project managersone : emotional intelligence importance for project managersone of the measurements of leadership is the eq emotional
Description of risk managementwrite a paper regarding a : description of risk managementwrite a paper regarding a project either real or fictitious where one is able to discuss
Given the following project to landscape a new building : given the following project to landscape a new building site.activityimmediate predecessoractivity
Project management of applicationsshow the role of the : project management of applicationsshow the role of the project manager in the in-house development of a customized
Project cash flow analysisyour company plans to produce a : project cash flow analysisyour company plans to produce a product for two more years and then to shut down production.
Earned value analysis - monitoring and controlling project : earned value analysis - monitoring and controlling project costonce your budget is planned and allocated across your
Question about milton manufacturing overhead activity based : question about milton manufacturing overhead activity based costingmilton manufacturing has four categories of

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd