Given the following information for a one-year project, answer the following questions: Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $23,000; EV = $20,000; AC = $25,000; BAC - $120,000

Explain what is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?

Use the schedule performance index (SPI) to estimate how long it will take to finish this project.

Reference no: EM13363207

Questions Cloud

Identify the risk the impact expected outcomethe course is : identify the risk the impact expected outcomethe course is corporate risk management.1 i have to make a risk register
Winsome manufacturing project scopeyou are a manager at : winsome manufacturing project scopeyou are a manager at winsome manufacturing company a company that produces plastic
Explanation of performance improvement projectshow a : explanation of performance improvement projectshow a performance improvement project you have been involved in or had
Is a project management certification without experience : is a project management certification without experience sufficient?if a person has been certified by a project
Given the following information for a one-year project : given the following information for a one-year project answer the following questions recall that pv is the planned
Difference between it project managers and traditional : difference between it project managers and traditional project managers.all projects are constrained by three factors
Emotional intelligence importance for project managersone : emotional intelligence importance for project managersone of the measurements of leadership is the eq emotional
Description of risk managementwrite a paper regarding a : description of risk managementwrite a paper regarding a project either real or fictitious where one is able to discuss
Given the following project to landscape a new building : given the following project to landscape a new building site.activityimmediate predecessoractivity

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd