Give the answer of muliple choice question

Assignment Help Operation Management
Reference no: EM131390465

1.Delaying noncritical activities to lower peak demand on resources is known as resource

A)Shifting

B)Effectiveness

C)Manipulating

D)Smoothing

E)Allocation

2.If resources are not adequate to meet peak demands, the resulting reschedule is termed

A)Resource-constrained scheduling

B)Time-constrained scheduling

C)Mandatory leveling

D)Project resource adjustment

E)Allocation

3.When developing a new software package, the software must be designed, the code must be written, and the code must be tested. This is an example of a ______ constraint.

A)Physical

B)Technical

C)Resource

D)Schedule

E)Time

4.Sam the project engineer has been scheduled to run the product system test at the same time he is to build a marketing prototype. This is an example of a ______ constraint.

A)Physical

B)Technical

C)Resource

D)Scheduling

E)Time

5.Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test. This is an example of a _________ constraint.

A)Physical

B)Technical

C)Resource

D)Scheduling

E)Time

6.All of the following are kinds of resource constraints except

A)Materials

B)People

C)Equipment

D)Information

E)All of the above are resource constraints

7.A special truck that George needs on his project has been scheduled on another project. This is a ______ constraint.

A)Working capital

B)People

C)Equipment

D)Information

E)Materials

8.Regina's boss has told her that her project is very important. If the critical path is delayed, she will be given whatever she needs to get it back on schedule. Her project is ________ constrained.

A)Time

B)Quality

C)Cost

D)Performance

E)Resource

9.Scheduling time-constrained projects focuses on resource

A)Demands

B)Increases

C)Assumptions

D)Utilization

E)All are

10.Resource leveling can provide

A)Lower peak demand

B)Reduced resource need over the life of the project

C)Reduced fluctuations in resource demand

D)Both A and B are

E)A, B, and C are all

11.In a resource-constrained project, which of the following is most likely to be changed?

A)The completion date

B)The budget

C)Project quality

D)Both A and B are equally likely

E)A, B, and C are all equally likely

12.In a resource-constrained project the second priority in assigning resources is usually given to activities with the

A)Smallest duration

B)Least slack

C)Most slack

D)Lowest identification number

E)Highest cost

13.Splitting an activity creates the following situation:

A)More people working on the same activity

B)There are possible startup and shutdown costs

C)A resource may be moved from one activity to another and then back

D)Both B and C are

E)A, B, and C are all

14.Which of the following is not one of the more common problems associated with scheduling multiproject resources?

A)Overall schedule slippage

B)Inefficient resource utilization

C)Resource bottlenecks

D)Both A and C are

E)A, B, and C are all

15.A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?

A)We are spending less than we should for the project

B)We are doing a good job managing the project

C)We should check to see if all the bills have been paid

D)Both A and B are

E)We can't be sure how the project is going

Reference no: EM131390465

Questions Cloud

What are the assessments used for identification : What are the assessments used for identification? What is the family involvement and role in the process? What resources are available to families? What instructional and assistive technology is used?
Calculate and plot the amplitude of the vibration : Knowing that the motor is constrained to move vertically, use computational software to calculate and plot the amplitude of the vibration and the maximum acceleration of the motor for motor speeds of 1000 to 2500 rpm
Discuss whether chrysler legally repossessed the automobile : The repossessor ignored him and took the car anyway. Koontz did not physically challenge or threaten the repossessor. Discuss whether Chrysler legally repossessed the automobile.
Plot the amplitude of the vibration : Solve Prob. 19.C4, assuming that a dashpot having a coefficient of damping c = 2.5 kN · s/m has been connected to the motor base and to the ground.
Give the answer of muliple choice question : A project budget report is showing our project as spending $35,000 against a budgeted amount of $40,000. Which of the following is true?Which of the following is not one of the more common problems associated with scheduling multiproject resources?
Are bensons taxes discharged by the proceedings : Benson goes into bankruptcy. His estate is not sufficient to pay all taxes owed. Are Benson's taxes discharged by the proceedings?
How you could improve on contribution by using technology : EDU 324- Select one contribution and determine if it is still prevalent today. Explain how you could improve on this contribution by using technology in your own classroom or school situation.
Do the employees take all the estate : Do the employees take all the estate? If so, under what conditions? If the general creditors received nothing at all, would these debts be discharged?
Determine the range of values of the speed of the trailer : Neglecting the mass of the wheels and assuming that the wheels stay in contact with the ground, use computational software to calculate and plot the amplitude of the vibration and the maximum vertical acceleration of the trailer for speeds of 10 t..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd