Reducing Project Duration

1. The president of a software company remarks in a speech that new technologically advanced software will be available in one year. This is an example of reducing project duration caused by:

A)Imposed project deadlines

B)Time to market

C)Unforeseen project delays

D)High overhead

E)Incentive contracts

2. Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by:

A)Imposed project deadlines

B)Time to market

C)Unforeseen project delays

D)High overhead

E)Incentive contracts

3. Which of the following is not considered a project indirect cost?

A)Supervision

B)Consultants

C)Equipment

D)Interest

E)All of these are considered project indirect costs

4. Low-cost, realistic, efficient methods for completing an activity under normal conditions are supported by ____ time.

A)Normal

B)Budget

C)Optimized

D)Expected

E)Target

5.The shortest possible time an activity can be completed realistically is called ___ time.

A)Expedited

B)Accelerated

C)Crash

D)Optimistic

E)Optimal

6.____ costs are incurred when completing an activity in its realistically shortest time.

A)Normal

B)Reserve

C)Crash

D)Accelerated

E)Expedited

7.Cost slope can be determined by dividing the

A)Run by the rise

B)Rise by the run

C)Crash cost by the normal cost

D)Normal cost by the crash cost

E)Both B and C are

8. Which of the following ly calculates an activity's cost slope?

A)(normal cost-crash cost)/(normal time-crash time)

B)(crash cost-normal cost)/(normal time-crash time)

C)(normal time-crash time)/(crash cost-normal cost)

D)(normal time-crash time)/(normal cost-crash cost)

E)(crash cost-normal cost)/(crash time-normal time)

9. The optimum duration for a project is at the point where:

A)Direct costs are the lowest

B)Indirect costs are the lowest

C)Direct costs equal indirect costs

D)Total project costs are the lowest

E)The project changes from time-constrained to resource-constrained

10.Creating a Project Cost-Duration graph is useful:

A)During the pre-project planning phase

B)After the project has begun

C)After the completion of the project

D)Both A and B are

E)A, B, and C are all

11. If a network has several critical or near-critical paths it is deemed to be:

A)Well planned

B)The lowest cost alternative

C)Resource-constrained

D)Sensitive

E)Insensitive

12.A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is:

A)Insensitive

B)Sensitive

C)Ahead of schedule

D)Shifting to the critical chain

E)Implementing a fast-tracking system

13.Which of the following is the most common method for shortening project time?

A)Assigning additional staff and equipment

B)Subcontract work

C)Schedule overtime

D)Reduce project scope

E)Reduce the quality

14.Which of the following is the easiest method for shortening project time?

A)Assigning additional staff and equipment

B)Subcontract work

C)Schedule overtime

D)Reduce project scope

E)Reduce the quality

15.The Snapshot from Practice "Cell-Phone Wars" is an excellent example of reducing project duration due to:

A)Imposed project deadlines

B)Time to market

C)Unforeseen project delays

D)High overhead

E)Incentive contracts

Reference no: EM131390457

Questions Cloud

Determine the range of values of the speed of the trailer : Neglecting the mass of the wheels and assuming that the wheels stay in contact with the ground, use computational software to calculate and plot the amplitude of the vibration and the maximum vertical acceleration of the trailer for speeds of 10 t..
What is jessicas status in the bankruptcy proceeding : If the security interest is invalidated, what is Jessica's status in the bankruptcy proceeding?- If the security interest is not invalidated, what is Jessica's status in the bankruptcy proceeding?
What would you say is the most important result of events : EDU 324- What would you say is the most important result of each of your chosen events? Two events are chosen and a Venn Diagram is completed showing the similarities and differences of each chosen event.
Were the debtors entitled to a discharge : Rosin off had falsely sworn that he had taken $70 from the partnership account when he had actually taken $700. Were the debtors entitled to a discharge?
Give the answer of muliple choice question : A positive situation where moving toward the optimum time can result in very real, large savings-this occurs when the network is.Which of the following ly calculates an activity's cost slope?The president of a software company remarks in a speech th..
Which of the given debts were completely discharged : A debtor went through bankruptcy and received his discharge. Which of the following debts were completely discharged, and which remain as future debts against him?
Common names of groups of organisms : List four classes of helminthes and indicate the common names of these groups of organisms?
The impact of our own species on earth discussion : The material covered in this module has shown that changes in global geology and climate over the past 3+ billion years have dramatically shaped the evolution of life on Earth.
How the courses in your curriculum directly contribute : You should explain how the courses in your curriculum directly contribute to the overall program outcomes you developed. You should have a few sentences of justification for each course.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd