Forward and backward pass through the network

Assignment Help Operation Management
Reference no: EM131039806

1. Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity

2. What is the project duration?

3. What is the critical path of this network?

4. Using any approach you wish (e.g., trial and error) develop a loading chart for the project resources: Carpenters (C) and Electricians (E). Assume only one Carpenter is available and two Electricians are available.

5. Using the resource loading chart, now compute the early/late start time, early/late finish time, and slack time for your project. Illustrate this new resource constrained network in a network diagram.

6. Complete the resource activity schedule.

7. For the new network, what is the new project duration?

8. Which activities are now critical?

Reference no: EM131039806

Questions Cloud

Management positions in chile with expatriates : Which of the following questions is LEAST relevant to the decision to fill management positions in Chile with expatriates?
What''s the origin of the ccc model : Where did Adam and Eve and other humans live during this "Adam to Noah" time and why don't we find massive gravesites of their bones?
Conducting an environmental analysis : Conducting an environmental analysis on an organization prior to developing a strategy is important. One way that health care managers conduct an environmental analysis is by identifying key industry-driving forces such as consumer demand, technol..
Differences between an attitude and a behavior : Part Two: Discuss the differences between an attitude and a behavior. Provide 4 substantive reasons why it is important for organizations to monitor and mitigate employee behavior that is either beneficial or detrimental to the organization's goa..
Forward and backward pass through the network : Complete the network diagram by conducting a forward and backward pass through the network. Compute the early/late start time, early/late finish time, and slack time for each activity. What is the project duration? What is the critical path of this n..
Draft a contract clause : Pick a clause to use for the assignment. Pick either Alternative Dispute Resolution (ADR) systems or intellectual property (IP).
What challenges did he face : What should the HR Manager recommend in terms of Parson's performance? Should Rob stay with the company? If so, how should the performance assessment and management system be altered?
Weaknesses of outsourcing the information technology : From the e-Activity, create an argument that highlights both the strengths and weaknesses of outsourcing the information technology responsibilities for a health care organization. Support your response with a list of at least three (3) functions ..
Abandon command-and-control styles : Complexity theorists advise organizational leaders to abandon command-and-control styles of management and instead set global performance targets and establish a few simple rules.

Reviews

Write a Review

Operation Management Questions & Answers

  Qualify as discontinuous innovation

Which of the following would NOT qualify as a discontinuous innovation? The growing success of low cost airlines in the travel market is an example of disruptive innovation. Cognitive maps are a useful methods to encourage creativity and promote inno..

  Why you believe diversity should be valued in the workplace

Legislation and hiring laws can be a benefit to the fire service if the personnel support it, why you believe diversity should be valued in the workplace and what personnel management can due to foster diversity

  What is the overall reliability of the system

A product is made up of two subsystems in parallel. Subsystem one consists of ten elements in series each with a failure rate of 1/100. The second subsystem consists of 5 elements in series each with a failure rate of 1/200. What is the overall re..

  Make the recommendation between these two countries

You are the CEO of a large company seeking to invest in either Central or South America and have directed your staff to prepare a report and recommendations. Two of the countries you are assigned are Brazil and Venezuela, and it is your task to make ..

  Examine persuasive requests and sales messages what traits

analyze persuasive requests and sales messages. what traits do persuasive requests and sales messages share in common

  Organizational restructuring is common as organizations

organizational restructuring is common as organizations attempt to achieve higher levels of performance. provide

  Demonstrate logical and appropriate transitions

Write your original response in Standard English, paying special attention to grammar, style, and mechanics. Respond to the questions in a thorough manner, providing specific examples of both the expected benefits and the risks/issues.

  Potential long term and short-term downside for the firm

If a firm enters into a strategic alliance but does not exercise appropriate behavioral control of its employees (in terms of culture, rewards and incentives, and boundaries—as discussed in Chapter 9) that are involved in the alliance, what ethical i..

  Largest bilateral trading relationship

Two-way trade between _ and the United States represents the worlds largest bilateral trading relationship.

  Participate to reach a suitable level of muscle strength

Did you experience any difficulties with the floor exercises tonight? If yes, how so? Or, was this easy for you? In other words, what were your strong muscles….what were your weak muscles? 2) Are you satisfied with the muscle strength in your abs, hi..

  Which alternative has the lowest break-even quantity

A firm is considering three capacity alternatives: A, B, and C. Alternative A would have an annual fixed cost of $100,000 and variable costs of $22 per unit. Alternative B would have annual fixed costs of $120,000 and variable costs of $20 per unit. ..

  The absolute weight of this customer requirement

A particular customer requirement is associated with a technical requirement, has an importance of 3, a target value of 5, and a sales point value of 2. The absolute weight of this customer requirement is ________.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd