Problem 1

Solve the following problem graphically (Please be neat) (Suggestion, use some graphing software such as GraphCalc® to create the feasible solution space. Then print that graph for your analysis): 
 
Maximize Z = 8x1 + 5x2 
Subject to:  

  -4x1 + x2 ≤ 1 
  3x1 + 4x2 ≤ 25 
  5x1 -2x2 ≤ 12 
  -1.5x1 + 3x2 ≤ 8 
 
and

x1,x2 ≥ 0  

Problem 2
 
Work through the simplex method (in algebraic form) step by step to solve the following problem. Show all work and provide the solution.  
 
  Maximize  Z = x1 + 3x2 + 2x3
subject to

    5x1 + 2x2 + 3x3 ≤ 15 
      x1 + 4x2 + 2x3 ≤ 12 
    2x1 +  x3 ≤   8 
and 
    x1 ≥ 0,    x2 ≥ 0,   x3 ≥ 0. 
 
Problem 3

My diet requires that all food I eat come from one of the four "Basic food groups" (chocolate cake, ice cream, soda, and cheesecake). At present, the following four foods are available for consumption: brownies, chocolate ice cream, cola, and pineapple cheesecake. Each brownie costs 50¢, each scoop of chocolate ice cream cost 20¢, each bottle of cola cost 30¢, and each piece of pineapple cheesecake cost 80¢. Each day, I must ingest at least 500 calories, 6 oz of chocolate, 10 oz of sugar, and 8 oz of fat. The nutritional content per unit of each food is shown in the following table. Formulate a linear programming model that can be used to satisfy my daily nutritional requirements at minimum cost.

2276_Formulate a linear programming model for problem.png

1. Formulate a linear programming model for this problem by:

A.  Listing and labeling all of the decision variables.

B.  Creating an objective function for the model.

C.  List all

2. Solve the model using Excel® solver. Give the value for each decision variable and the objective function.

Problem 4.

The Weigelt Corporation has three branch plants with excess production capacity. Fortunately, the corporation has a new product ready to begin production, and all three plants have this capability, so some of the excess capacity can be used in this way. This product can be made in three sizes--large, medium, and small--that yield a net unit profit of $420, $360, and $300, respectively. Plants 1, 2, and 3 have the excess capacity to produce 750, 900, and 450 units per day of this product, respectively, regardless of the size or combination of sizes involved.

  The amount of available in-process storage space also imposes a limitation on the production rates of the new product. Plants 1, 2, and 3 have 13,000, 12,000, and 5,000 square feet, respectively, of in-process storage space available for a day's production of this product. Each unit of the large, medium, and small sizes produced per day requires 20, 15, and 12 square feet, respectively.

  Sales forecasts indicate that if available, 900, 1,200, and 750 units of the large, medium, and small sizes, respectively, would be sold per day.

  At each plant, some employees will need to be laid off unless most of the plant's excess production capacity can be used to produce the new product. To avoid layoffs if possible, management has decided that the plants should use the same percentage of their excess capacity to produce the new product.

  Management wishes to know how much of each of the sizes should be produced by each of the plants to maximize profit.

1. Formulate a linear programming model for this problem by:

D.  Listing and labeling all of the decision variables.

E.  Creating an objective function for the model.

F.  List all

2. Solve the model using Excel® solver. Give the value for each decision variable and the objective function. 

Problem 5. For the project schedule, answer the following questions.  

1.  What is the total time required to complete the project if no delays occur? 
 
2.  When do the individual activities need to start and finish (at the latest) to meet this project completion time? 
 
3.  When can the individual activities start and finish (at the earliest) if no delays occur? 
 
4.  Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion? 
 
5.  For the other activities, how much delay can be tolerated without delaying project completion?

781_Formulate a linear programming model for problem1.png

598_Formulate a linear programming model for problem2.png

6.  Suppose the following data is given pertaining to the cost associated with crashing activities. What activities should be crashed and how much will it cost if the deadline is changed to: 
 
a.  19 weeks

b.  18.5 weeks

c.  18 weeks

d.  17.5 weeks

e.  17 weeks

f.  16.5 weeks

g.  16 weeks

h.  15.5 weeks

i.  15 weeks 
 
7. Plot the cost of time reduction against total time reduction and draw any conclusions. What happens to the cost as the amount of time reduction is increases?

1396_Formulate a linear programming model for problem3.png

Reference no: EM13169915

Questions Cloud

Calculate the molarity of the kcl solution : 12.5 g of KCl (MM = 74.55 g/mol) is dissolved in enough water to make 675 mL of solution. Calculate the molarity of the KCl solution.
Which of the following is a neutralization reaction : which of the following is a neutralization reaction? 2no2 --> 2no-> + 02, h2o+so3-->h2so4, hno3 +koh-->h2o+kno3, 4na+o2 --> 2na2o, kcl+nano3--> kno3 + nacl
How many grams of fes2 and o2 are left : if 294 grams of is allowed to react with 176 grams of according to the following unbalanced equation, how many grams of are produced? How many grams of FeS2 and O2 are left?
Philospher john locke believed : The philospher john locke believed that people? sensation has no effect on perception. the perceived whole differs from the sum of its parts.
Formulate a linear programming model for problem : Plot the cost of time reduction against total time reduction and draw any conclusions. What happens to the cost as the amount of time reduction is increases?
Peer-reviewed academic sources : Research at least four (4) peer-reviewed academic sources.  Analyze and explain four (4) critical trends affecting the growth of public personnel today.  Analyze and evaluate four (4) strategies needed to create a diversified workforce.
How much heat is released per gram of oil shale : The calorimeter contains 1.00 kg of water (heat capacity of H2O = 4.184 J/g°C) and the heat capacity of the empty calorimeter is 0.10 kJ/°C. How much heat is released per gram of oil shale when it is burned?
Demographic pyramid : Describe ongoing changes in the age distribution of the American population, noting the current shape of the “demographic pyramid.” What ramifications are there for these changes?
What mass of iron would be required to cover a football : Iron has a density of 7.87 g/cm3. What mass of iron would be required to cover a football playing surface of 120 yds × 60 yds to a depth of 10 mm? (1 inch = 2.54 cm; 1 lb = 453.6 g)

Reviews

Write a Review

Operation Research Questions & Answers

  Bioimetic vascular network design

What kind of material is needed for bioimetic vascular network design?

  Write a report on im operations governance

Write a report on IM operations governance

  Analyse the role of different stakeholders in tourism

Critically analyse the role of different stakeholders in tourism planning and policy

  Evaluate business value

How can internet technologies be involved in improving a process in one of the functions of business? Choose one example and evaluate its business value.

  Case study:the british airways story

Case study:The British Airways story

  Prepare a research proposal

Prepare a Research Proposal based on a business issue.

  Create the feasible solution space

Solve the following problem graphically and create the feasible solution space.

  Calculate annual rate of return

No additional fixed costs would be incurred if this proposal is accepted

  Compute the company''s predetermined overhead rate

Corporation bases its predetermined overhead rate on the estimated labor hours for the upcoming year

  Determine the probability distribution

Determine the probability distribution for demand using the given data.

  Give both a high-level algorithm and an implementation

Give both a high-level algorithm and an implementation (\bubble diagram") of a Turing machine for the language

  Red brand canners

Red Brand Canners Gordon asked Myers about the demand for tomato products for the coming year. Myers replied that they could sell all of the whole canned tomatoes they could produce.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd