Long-Term Construction Contracts:
Forman Company has contracted to build a dam over a period of 4 years for $3,000,000. Information relating to the performance of the contract is summarized as follows:
1. a. Compute the profit or loss for each year of the contract under the percentage-of-completion method. Enter losses as a negative number.
2013
|
2014
|
2015
|
2016
|
$
|
$
|
$
|
$
|
b. Compute the profit or loss for each year of the contract under the completed-contract method. Enter losses as a negative number.
2013
|
2014
|
2015
|
2016
|
$
|
$
|
$
|
$
|
2. a. Prepare the relevant sections of the income statement for each year under the percentage-of-completion method.
|
2013
|
2014
|
2015
|
2016
|
Construct Revenue
|
$
|
$
|
$
|
$
|
Construction Expense
|
|
|
|
|
Gross Profit (loss)
|
|
|
|
|
Prepare the relevant sections of the ending balance sheet for 2013 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
XXXXXXX
|
XXXXXXXX
|
Accounts Receivable
|
XXXXXXXX
|
$
|
Inventory
|
XXXXXXXX
|
XXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXX
|
Costs and recognized profit not yet billed
|
XXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2014 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
XXXXXXXX
|
XXXXXXXX
|
Accounts Receivable
|
XXXXXXXX
|
$
|
Inventory
|
XXXXXXXX
|
XXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXX
|
Costs and recognized profit not yet billed
|
XXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2015 under the percentage-of-completion method.
Balance Sheet
|
Partial
|
12/31/13
|
Current Assets
|
XXXXXXXXXXXX
|
XXXXXXXXXX
|
Accounts Receivable
|
XXXXXXXXXX
|
$
|
Inventory
|
XXXXXXXXXXX
|
XXXXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXXXX
|
Costs and recognized profit not yet billed
|
XXXXXXXXXXX
|
$
|
b. Prepare the relevant sections of the income statement for each year under the completed-contract method. Enter losses as a negative number.
Income Statement (Partial) Years 2013 through 2016
Prepare the relevant sections of the ending balance sheet for 2013 under the completed-contract method.
Current Assets
|
XXXXXXXXXX
|
XXXXXXXXX
|
Accounts Receivable
|
XXXXXXXXXX
|
$
|
Inventory
|
XXXXXXXXXXXXX
|
XXXXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXXXXX
|
Excess of Costs over related billings
|
XXXXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2014 under the completed-contract method.
Current Assets
|
XXXXXXXXXXXX
|
XXXXXXXXXX
|
Accounts Receivable
|
XXXXXXXXXXX
|
$
|
Inventory
|
XXXXXXXXXXX
|
XXXXXXXXXXX
|
Construction in progress
|
$
|
XXXXXXXXXX
|
Less:Partial Billings
|
$
|
XXXXXXXXXX
|
Excess of Costs over related billings
|
XXXXXXXXXXXXX
|
$
|
Prepare the relevant sections of the ending balance sheet for 2015 under the completed-contract method.
Current Assets
|
|
|
Accounts Receivable
|
|
$
|
Inventory
|
|
|
Construction in progress
|
$
|
|
Less:Partial Billings
|
$
|
|
Excess of Costs over related billings
|
|
$
|
Cost-based pricing
: Otero Fibers, Inc., specializes in the manufacture of synthetic fibers that the company uses in many products such as blankets, coats, and uniforms for police and firefighters. Otero has been in business since 1985 and has been profitable every year ..
|
Equation of the least-squares regression line
: The equation of the least-squares regression line for predicting average number of offspring per female from cone index is
|
Problem regarding the percent of the students
: (i) If he allows 20 minutes for the quiz, what percent of the students will not complete the quiz? (ii) Suppose that he wants to allow sufficient time so that 95% of the students will complete the quiz in the allotted time. How much time should he..
|
What ultimately were these codes designed to do
: During Reconstruction, Black Codes were enacted in several former states in the Confederacy. A Republican controlled Congress would later react to suppress these codes - What ultimately were these codes designed to do?
|
Forman company has contracted to build a dam over a period
: Forman Company has contracted to build a dam over a period of 4 years for $3,000,000. Information relating to the performance of the contract is summarized as follows:
|
Provide background information about education
: Provide an in-depth definition and components about the topic. Provide background information about the topic (developed from the 3 resources discovered). Apply 3 different sociological theories to the topic.
|
The back-end database
: Three (3) page Word document that describes the front-end, the user interface, and the back-end database and how the requirements were met, and a full description of client needs and how the application supported the requirements.
|
Problem regarding the mechanical measurements
: Mechanical measurements on supposedly identical objects usually vary. The variation often follows a Normal distribution. The stress required to break a type of bolt varies Normally with mean 75 kilopounds per square inch (ksi) and standard deviati..
|
Explain what made you want to research that topic
: LING 102: Spring 2016 - Research Paper Presentation - You will need to consider the sequence of the information you will share to make sure it will occur in a logical fashion. Also consider transition use.
|