Forest point construction-what is the critical path

Assignment Help Operation Management
Reference no: EM13870539

Forest Point Construction

At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience. You are trying to convince him that he should use project management techniques to handle a complex project.

To prove your point, you decide to use a simple example of a commercial steel building construction project, with eight steps. You create a hypothetical work breakdown structure, as follows:

Prepare the site (3 days), and then set the building footers (3 days).

Finish the foundation (5 days), and then assemble the building (3 days).

When the building is assembled, start two tasks at once: finish the interior work (5 days) and set up an appointment for the final building inspection (15 days).

When the interior work is done, start two more tasks at once: landscaping (7 days) and driveway paving (3 days).

When the landscaping and driveway are done, does the painting (2 days).

Finally, when the painting is done and the final inspection has occurred, arrange the sale (2 days).

Now you ask your boss to review the tasks, estimate the total time, and write the answer on a piece of paper. You look at the paper and see that his guess is wrong.

Tasks

What is the correct total time?

What is the critical path?

Create a Gantt chart that shows the WBS.

Create a PERT/CPM chart.

Reference no: EM13870539

Questions Cloud

Mass production reduce duplication of equipment : An individual who accepts the risks and opportunities entailed by creating and operating a new business is a(n) ___________. During which period did mass production reduce duplication of equipment and allow firms to purchase raw materials at better p..
Differ for organizational buying compared to consumer buying : One way that marketing mix characteristics differ for organizational buying compared to consumer buying is that for organization buying
Most large airlines operate networks-hub-and-spoke systems : Most large airlines operate networks, hub-and-spoke systems, which connect many spoke cities (or nodes) with flights to and from a hub airport. How can a network airline profitably serve smaller cities than a low-cost-airline?
Which myth of motivation is the most important : Motivation is not a new concept, so why is motivation important? Is it more important that an employee is motivated or engaged? Which myth of motivation is the most important? Are there other myths that you can identify?
Forest point construction-what is the critical path : At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience. You are trying to convince him that he should use project management techniques to handle a complex project. What is the critic..
Training session for new employees at brightstar industries : You will lead a training session for new employees at Brightstar Industries. You must develop a specific schedule for the following tasks (the estimated duration is shown in parentheses): Prepare a list showing all tasks and their durations. Analyze ..
Demonstrating spatial cues-practicing time management : Aliyah prepares a to-do list of all the tasks she needs to complete within the week. First, she completes high-priority tasks. She then divides her large tasks into smaller ones, so they are easier to undertake. At the end of the week, she evaluates ..
Issues our environment faces is human impact : One of the issues our environment faces is human impact, and how human actions through development and technology create environmental surprise. As much as the world needs to develop, it must temper its development to ensure adequate environmental ma..
What is sustainable development : Several factors affect sustainable development with the key component being natural resources that are both renewable and non-renewable. What is sustainable development? Discuss the factors that influence the viability of sustainable development with..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd