Forest Point Construction
At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience. You are trying to convince him that he should use project management techniques to handle a complex project.
To prove your point, you decide to use a simple example of a commercial steel building construction project, with eight steps. You create a hypothetical work breakdown structure, as follows:
Prepare the site (3 days), and then set the building footers (3 days).
Finish the foundation (5 days), and then assemble the building (3 days).
When the building is assembled, start two tasks at once: finish the interior work (5 days) and set up an appointment for the final building inspection (15 days).
When the interior work is done, start two more tasks at once: landscaping (7 days) and driveway paving (3 days).
When the landscaping and driveway are done, do the painting (2 days).
Finally, when the painting is done and the final inspection has occurred, arrange the sale (2 days).
Now you ask your boss to review the tasks, estimate the total time, and write the answer on a piece of paper. You look at the paper and see that his guess is wrong.
Tasks
1. What is the correct total time?
2. What is the critical path?
3. Create a Gantt chart that shows the WBS.
4. Create a PERT/CPM chart.
Design of the Constitution is separation of powers
: A major principle guiding the design of the Constitution is separation of powers. Which of the following is part of the separation of powers principle?
|
Write a paper on domestic violence
: Write a paper on Domestic violence
|
Articles of confederation and the new constitution
: Which of the following is one of the differences between the Articles of Confederation and the new Constitution created during the Constitutional Convention in 1787?
|
Electoral system and federalism affect the shape of parties
: Is there evidence that a party realignment is occurring in the United States? What is the organizational structure of political parties? What are some of the functions of parties in the electoral arena? How do both the electoral system and federalism..
|
Forest point construction
: At Forest Point Construction, your boss says that he can estimate the total project time based on his personal experience. You are trying to convince him that he should use project management techniques to handle a complex project. What is the correc..
|
Deferred annuity where monthly withdrawals begin
: What lump sum of money (P) must be deposited into a bank account at the present time so that $500/month (A) can be withdrawn for five years (N), with the first withdrawal scheduled 6 years from today at a nominal interest rate (r) of 9% per year? [Hi..
|
Find limit output for fixed costs-stackelberg equilibrium
: Suppose that inverse demand is given by D(Q) = 56 − 2Q, Q = q1 + q2 and the cost function is TC(qi ) = 20qi + f Find the Stackelberg equilibrium and compare it to the Cournot equilibrium. 6. What is the SPNE for the entry game with the following timi..
|
Quantitative analysis and decision-making
: Quantitative Analysis and Decision-Making
|
How much profit does the firm collect with the prices set
: Suppose there are two types of customers for a cell phone service: undergraduates (U) and grad Students (G). The aggregate (inverse) demand curve for undergraduates is PU = 100 − 0.25QU and the aggregate (inverse) demand curve for the graduate studen..
|