Five Star Hotel ELV Extra Low Voltage Project

Five Star Hotel ELV (Extra Low Voltage) Project Located in Bahrain, the Five Star Hotel ELV project was completed in 2011. The purpose of this project was to install, test, and commission the IT, communication infrastructure, and services for the hotel. The ELV project was part of a total program to deliver 11 sub-systems, including installation of data, voice, music, wireless, and CCTV systems. The project stakeholders included the hotel owner; the consultant they had employed on their behalf; and various civil, electrical, and construction teams involved in implementing the ELV project. This case study focuses on the Audio Visual (AV) sub-system, primarily installation of projectors and screens in the meeting rooms and conference facilities. Renosh Thomas, as the vendor's project manager, was responsible for issuing the client with complete drawings detailing the projects electrical requirements. Renosh knew these drawings needed to be accurate as these would be handed over to the civil and construction teams for use when building the sites. Bearing this dependency in mind, Renosh ensured his team completed accurate and timely drawings with the expectations that the civil and construction teams would complete the build and handover a completed room with all the electrical requirements as planned. The final phases of the ELV project required Renosh's team to visit the sites, install, and test the electrical equipment. At initiation and during the project's planning phases, the AV requirements were issued and communicated via drawings between the consultant, appointed by the customer, and Renosh's electrical team. The product specifications were based on lessons learned and templates from a similar project implemented in Dubai. The project scope was determined via the bill of quantities, materials, and tender documents. Renosh received only electrical drawings for the sites and continued to plan the installation requirements based on these drawings, going by the assumption that they were correct, accurate, and most recent. Throughout planning, the electrical team was not privy to any of the civil or construction drawings from the other teams, and hence remained completely unaware of structural changes being made on the original plans that they were still working on too.

During installation of the AV system, the team encountered a major problem- the projection was faulty. The projectors and screens were not aligning, causing the projected images to be cut off and unclear. Upon investigation it became apparent that certain structural changes had been added, making Renosh's drawings and calculations inaccurate. The customer's response to this communication oversight was to respond by sending Renosh a full collection of civil and construction drawings including all the latest revisions. Renosh spent considerable time reviewing the drawings to identify the relevant adjustments. This resulted in delays, rework, and wasted time as he ploughed through the drawings, many of which were excessive to his requirements. The problem the installation team encountered was that the ceilings had been elevated higher than the original design and this had been approved by the customer, who failed to communicate the new changes and approvals to Renosh's electrical team. The solution required changing the location of the projector by a meter and the screens had to be moved forward by centimeters. Renosh revised and issued new electrical drawings to the customer that went through the approval process again. The site had been handed over from civil and construction completed with decoration. However, this vital communication error resulted in the solution requiring reworking of parts of the site, such as opening the ceilings to access the electrical panels and make the new changes. This impacted the schedule by 8- 10 days, and reworked costs of opening, adjusting, and redecorating the site.

Questions

1. How did the project's scope of changes impact the project stakeholders?

2. What planning, monitoring, and control actions could the project manager take to avoid the situation?

3. How would you redesign the communications management processes to minimize the problems experienced by project managers?

Reference no: EM132348462

Questions Cloud

Important project planning document : The Project Scope Statement is an important project planning document because the Scope Statement: (select all that apply)
Development of the scientific method impacts our worldview : Explore how the development of the scientific method impacts our worldview. Identify the initial observations that identified the problem,
Clear detail the specific steps that the robot : Assume that a robot that can wash cars is being designed. Your job is to write out in clear detail the specific steps that the robot will take.
Integrate the risk management processes : How would I write a personal Risk Management Guide, to prepare someone to integrate the risk management processes?
Five star hotel elv extra low voltage project : Five Star Hotel ELV (Extra Low Voltage) Project Located in Bahrain, the Five Star Hotel ELV project was completed in 2011. The purpose of this project was
Define potential and kinetic energy : Define Potential and Kinetic energy. What are the units associated with these? Explain both types of energies with at least 5 different examples.
What does the story of the chilean miners rescue : What does the story of the Chilean miners rescue suggest to you about the variety of ways that project management can be used in the modern world?
Connect the principles of electricity and magnetism : Connect the principles of electricity, magnetism and light to modern applications of physics. Explain how these principals connect to electricity, magnetism,
Project task estimation and the culture of gotcha : I recently worked with an organization that adopted a mind-set in which it was assumed that the best way to keep project team members working

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd