Q1) Given following information about staging a community play on Independence Day.
a) Create a PDM/CPM diagram.
b) Find out the earliest completion time for play and critical path
c) Based on critical path, what completion date are you 80% confident of achieving? 40% confident?
d) Will a 1-day delay in this project be serious?
Time (days)
Activity
Predecessor
a
m
b
1
-
2
4
6
5
3
7
10
13
11
12
2,4
9
8
3,6
15
17
19
9,10
14
16
Is the school district correct in assuming the girls are equal in performance to boys. They are 95% sure their assumption is correct.
At the .01 significance level, is there a relationship between job pressure and age?
Does the overall data support the mayor's claim?
Using part(a), explain to investor differences between distribution of performance figures for the 2 kinds of stock funds.
For following scores determine values of each expression: X: 4, 2, 1, & 5. åX, åX 2 , (åX) 2 , å(X-1).
At α = 0.01 level of significance, test the hypothesis that these data can be described by a Poisson pdf.
Based on the information, what decision should the director make about the books used for the courses if the goal is to keep the cost below $300?
Find out the crude death rate, age specific death rate, standard death rate and adjusted death rate.
In a survey conducted to see how long Americans keep their cars, 2000 automobile owners were asked how long they plan to keep their present cars. The results of the survey follow. Find out the probability distribution associated with these data.
Does the normal distribution yield a good approximation of the actual results?
They are thinking of introducing a new flavour, maple-marshmallow Frumpies, and want to know whether children will prefer the new flavour to the old one. Design a completely randomized experiment to investigate this question.
Determine the probability that the project will be completed in 90 days or less.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd