Crede Manufacturing Company uses a standard cost accounting system. In 2020, 27,000 units were produced. Each unit took several kilograms of direct materials and 1.6 standard hours of direct labour at a standard hourly rate of $15. Normal capacity was 49,600 direct labour hours. During the year, 113,400 kg of raw materials were purchased at $0.92 per kilogram. All materials purchased were used during the year.
Question 1: If the materials price variance was $9,072 favourable, what was the standard materials price per kilogram? (Round answer to 2 decimal places, e.g. 5.25.)
Question 2: If the materials quantity variance was $5,400 unfavourable, what was the standard materials quantity per unit? (Round answer to 2 decimal places, e.g. 5.17.)
Question 3: What were the standard hours allowed for the units produced?
Question 4: If the labour quantity variance was $10,950 unfavourable, what were the actual direct labour hours worked?
Question 51: If the labour price variance was $21,965 favourable, what was the actual rate per hour? (Round answer to 2 decimal places, e.g. 15.25.)
Question 6: If total budgeted manufacturing overhead was $386,880 at normal capacity, what was the predetermined overhead rate? (Round answer to 2 decimal places, e.g. 15.25.)
Question 7: What was the standard cost per unit of product? (Round answer to 2 decimal places, e.g. 15.25.)
Question 8: How much overhead was applied to production during the year?
Question 9: Using selected answers above, what were the total costs assigned to work in process? (Round answer to the nearest whole dollar, e.g. 5,275.)
What is the partial pressure of the third gas
: The individual pressures exerted by neon and argon are 0.68 atm and 0.35 atm, respectively. What is the partial pressure of the third gas, helium?
|
What is the volume of the solution in milliliters
: If 2.24 of CuNO3 is dissolved in water to make a 0.740 M solution, what is the volume of the solution in milliliters?
|
How solve the net present value of the project
: Calculate the Net Present Value of this project.Equipment costing $300,000 will be required immediately. The equipment will be straight line depreciated
|
Discovery health turns big data into better healthcare
: How big is big data for Discovery Health? What big data sources did Discovery Health use for their analytic solutions?
|
Find what were standard hours allowed for units produced
: If the labour price variance was $21,965 favourable, what was the actual rate per hour? (Round answer to 2 decimal places, e.g. 15.25.)
|
How many performance obligations exist in this contract
: Ortiz delivered and installed the equipment and software on August 1, 2021, How many performance obligations exist in this contract
|
Forensics to speed up the process of collecting data
: What can we do in forensics to speed up the process of collecting data? Hypothesize a solution knowing what you know about network data collection.
|
What is value of ending inventory under absorption costing
: 25,000 units, and sold 20,000 units, leaving 5,000 units in inventory at year-end. What is the value of ending inventory under absorption costing?
|
What is the volume of the solution in milliliters
: If 2.24 of CuNO3 is dissolved in water to make a 0.740 M solution, what is the volume of the solution in milliliters?
|