Cox Engineering performs cement core tests in its laboratory. The following standards have been set for each core test performed:

                              Standard Hours or Quantity      Standard Price or Rate
Direct materials                   3.0 pounds                      £0.75 per pound
Direct labour                        0.4 hours                       £12.00 per hour
Variable manufacturing overhead   0.4 hours                     £9.00 per hour

During March, the laboratory performed 2,000 core tests. On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core tests on the basis of direct labour hours. The following events occurred during March:

  1. 8,600 pounds of sand were purchased at a cost of £7,310.
  2. 7,200 pounds of sand were used for core tests.
  3. 840 actual direct labour hours were worked at a cost of £8,610.
  4. Actual variable manufacturing overhead incurred was £3,200.

Problem 1: The materials quantity variance for March is:

Multiple Choice

Option 1: £1,950 unfavourable.
Option 2: £ 900 unfavourable.
Option 3: £900 favourable.
Option 4: · £1,950 favourable.

Reference no: EM132714151

Questions Cloud

Describe confidence interval : Describe an odds ratio. Describe relative risk. Describe a confidence interval (CI).
Calculate the underwriter spread : Calculate the underwriter's spread in dollars per share on the stock issue. (Round your answer to 3 decimal places.)
Community health assessments : Community health assessments are used by health planners to identify, and prioritize health problems within a given community.
Estimate the cash price of a bond with a face value : Estimate the cash price of a bond with a face value of 100 that will mature in 30 months and pays a coupon of 3% per annum semiannually.
Find what the materials quantity variance for march is : Find what the materials quantity variance for March is? On March 1 no direct materials (sand) were on hand. Variable manufacturing overhead is assigned to core
What value should be placed on the purchase consideration : The fair value of the purchase consideration was 10 million ordinary shares of P1 of Die, What value should be placed on the purchase consideration
Equivalent rate with annual compounding : What is the equivalent rate with annual compounding? Enter your answer in percentage rounded to two decimals places (e.g, 15.45%)
Definition of least restrictive environment : What is the special education coordinator's definition of least restrictive environment (LRE)?
What is a currency : What is a currency? Does Bitcoin meet the classical definition of a currency? Why or why not?

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd