Find the variance and evaluate the cause of labor efficiency

Assignment Help Managerial Accounting
Reference no: EM132808952

The following labor standards have been established for a particular product:

Standard Labor - Hours per unit of output          2.00 hours
Standard labor rate                                    $ 12.40 per hour

The following data pertain to operations concerning the product for the last month:

Actual hours worked      7,200 hours
Actual Total labor cost    $ 88,000
Actual Output               1,550 units

Problem 1: Determine the variance and evaluate the cause of labor efficiency variance for the month.

Reference no: EM132808952

Questions Cloud

What is the realized gross loss to be recognized : What is the realized gross loss to be recognized by the entity for the year ended December 31, 2021 under percentage of completion method?
Compute the intangible assets to be recognized in statement : Patent A was purchased for P 1,920,000 on January, Compute the Intangible assets to be recognized in the statement of financial position as of December 31, 2020
Organization after adopting circular economy elements : Description of the organization after adopting the circular economy elements - focus onoperations and benefits.
What is the additional funds needed for the coming year : The firm is operating at full capacity. Data for use in your forecast are shown below. Based on the AFN equation, what is the AFN for the coming year?
Find the variance and evaluate the cause of labor efficiency : Find the variance and evaluate the cause of labor efficiency variance for the month. Data pertain to operations concerning the product for the last month
Determine the methods for estimating project costs : Explain the factors that determine how a company selects a project. Determine the methods for estimating project costs.
Compute the materials price variance for july : Unfavorable; and the standard quantity of materials allowed for July production was 19,215 pounds. Compute the materials price variance for July.
Evaluate the cause of labor efficiency variance : Determine the variance and evaluate the cause of labor efficiency variance for the month. Labor standards have been established for a particular product
Analyze the goals of the company : Analyze the goals of the company. What is an operating structure and how can changes affect a company?

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd