Project Scheduling and Cost Planning Assignment - EVM
Instructions: You are the project manager of a software development project. The team members will be working on five different components. Each of the components is budgeted to be $2,625, and all components are supposed to be completed in five weeks. Using the status in the following table, find the following values at the end of week four.
Project
Planned End Date
Planned Budget
Actual Amount Spent by Week Four
Planned Completion by Week Four
Actual Completion by Week Four
Software Development Project
End of 5th week
$13, 125 for total project or $2,625 for each component
$9,000
Four out of five components
Three out of five components
Acronym
Term
Formula
Answer
Interpretation
PV
EV
AC
SV
CV
CPI
SPI
BAC
EAC
ETC
VAC
TCPI
Requirements:
Be sure to read the criteria, by which your paper/project will be evaluated, before you write, and again after you write.
Evaluation Rubric for EVM Assignment- Justifications for reserve fund are based on clear estimations using EMV calculations and or PERT. The estimations are complete and matches the justifications. All activities are Sequenced using the predecessors’ column with a closed network diagram. At least 4 of your tasks relationships must be different than Finish to Start. Cost baseline include all activity cost estimates and when added up equals the cost baseline and contingencies. Summary budget fully updated to include cost baselines estimates.
An effective project manager needs a variety of both technical and business skill sets and find the non-technical skills that have been associated with superior project management.
Why is it wrong to manage change efforts from personal space in office and home rather than implemented in an organization?
What can be done to lower turnover in large restaurants? - Why is seniority important in scheduling servers? - How does the schedule impact productivity?
How would you assess the level of ethical interpersonal communication in organization at which you are or have been employed?
Identification of how beliefs, attitudes, and perceptions will impact this plan overall. How the plan will be communicated within organization?
Explain the trade-offs that can be made among requirements, cost, and schedule. For a given set of requirements, explain how cost and schedule can be traded off.
Describe this in that panel's interpretation. How does this new column enhance the original data or the display?- Create user interactivity with a filter on the panel.
What are the affects of a floating rate coupon on the coupon rate of a bond?
What occurs if the company decides to repatriate earnings? How should operating taxes be computed in the year of repatriation? How is ROIC distorted by foreign taxation and repatriation?
If? $6000 is invested for six years and seven months at? 6% compounded? semi-annually, what is the interest that the investment? earns?
Identify and recommend a new tax submission system software option.- write the implementation plan for the newly recommended software system.
Using the probability approach to determine an inventory safety stock and wanting to be 95 percent sure of covering inventory demand
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd