Consider a manufacturing process consisting of three activities:
• Activity 1 takes ten minutes to complete and there are two workers that work in parallel.
• Activity 2 takes six minutes to complete and there is only one worker.
• Activity 3 takes 15 minutes to complete and there are three workers that work in parallel.
a. What is the flow rate if demand is 4 units/hour?
b. What is the flow rate if demand is 15 units per hour?
c. What is the bottleneck if demand is 15 units per hour?
d. What is the utilization of each resource if demand is 15 units per hour?
e. Find the shortest time to fulfill an order of 1000 units.
f. Assume that each worker costs 12 TL/hour. Find the direct labor cost/item when demand is 4 units/hour and when demand is 15 units/hour.
g. What would be the flow rate if one worker is added to stage 2 if demand is 15 units per hour?
h. Find a fractional worker assignment (i.e. 1.5 workers to resource 1, 0.8 workers to resource 2 etc.) that would maximize the flow rate. What is the flow rate under this assignment if demand is 15 units per hour? What is the direct labor cost/item?
i. What would be the flow rate if n workers are added to the system in part h?
How many watts of power did she developed
: A 60.0 kg student runs up a 5.00 m high stairway in a time of 3.92 seconds. How many watts of power did she developed.
|
Electromagnetic waves produced
: A local FM radio station broadcasts at a frequency of 99.0 MHz. What is the wavelength, in meters, of the electromagnetic waves produced?
|
Problem regarding the person average speed
: A person takes a trip, driving with a constant speed of 89.5km/h , except for a 22.0 min rest stop. if the person's average speed is 77.8km/h a>how much time is spent on the trip and b>how for does the person travel?
|
Consider a pair of wave functions
: Consider a pair of wave functions, Ψ1 and Ψ2 that are orthonormal. Show that Ψ3 = Ψ1 + Ψ2 and Ψ4 = Ψ1 - Ψ2 can also be normalized, and that Ψ3 and Ψ4 are orthogonal to each other
|
Find the shortest time to fulfill an order of 1000 units
: Assume that each worker costs 12 TL/hour. Find the direct labor cost/item when demand is 4 units/hour and when demand is 15 units/hour.
|
Differences between work and power
: What are the significant similarities and differences between work and power?
|
Grand bahama is the hurricane
: The eye of a hurricane passes over Grand Bahama Island in a direction 60.0°north of west with a speed of42.0km/h.Three hours later, the course of the hurricane suddenly shifts due north, and its speed slows to24.0km/h.How far from Grand Bahama is ..
|
Change the kinetic energy at the same speed
: A bicycle and rider have a combined mass of 70.0 kg and are moving at 6.00 m/s. A 70.0 kg person is now given a ride on the bicycle (total mass 140.0 kg). How did the addition of the new rider change the kinetic energy at the same speed?
|
What is the speed of the satellite
: An Earth satellite moves in a circular orbit629km above the Earth's surface. The period of the motion is97.1min.
|