Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. a. Find the production capacity of the line for the following assignment: Worker 1 → Task 1, Worker 2→ Task 2, Worker 3→Tasks 3,4, Worker 4→ Tasks 5,6. b. Find optimal assignment (to maximize the production capacity) if the task sequence should not be broken (task j should be done before task j +1). c. Find optimal assignment (to maximize the production capacity) if the task sequence can be broken (no precedence relationship between tasks). 1 d. Assume that the daily demand for this item is 400 and that each worker costs 15 TL/hr. Find the direct labor cost per item if the task sequence should not be broken.

Reference no: EM131396585

Questions Cloud

Protection against damage caused by acts of god : You are a risk manager in a manufacturing company. One of your key responsibilities is securing of property insurance coverage to provide protection against damage caused by “acts of God,” such as earthquakes, hurricanes, floods, etc. Determine where..
Publicly funded alcohol and drug treatment program : As a counselor working at a publicly funded alcohol & drug treatment program. Your client, Doug, attends one of your counseling groups. Although he has a previous conviction & is on probation for possession of an illegal substance, he entered treatme..
Find the average tardiness and the number of jobs : A make-to-order system has 6 jobs to complete on a single machine. Let tj denote the time (in minutes) to complete job j. We have: t1 = 30, t2 = 25, t3 =35,t4 =40,t5 =15,t6 =30. Assume that these t up time for each job is 10 minutes. Find the average..
Manufacturing process consisting of three activities : Consider a manufacturing process consisting of three activities: Activity 1 takes ten minutes to complete and there are two workers that work in parallel. Activity 2 takes six minutes to complete and there is only one worker. Activity 3 takes 15 minu..
Find the production capacity of the line : Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. Find..
Discuss steps used in determining how to select media venue : Discuss the steps used in determining how to select a media venue. Describe each of the five W’s for your media planning. Describe the three most important rules of media buying and why they apply to your client.
Just-in-time replenishment-tight inventory control systems : Office Depot sells a wide range of office supply products and services in the United States and internationally. The company tries to offer a wider range of office supplies at lower cost than other retailers by using just-in-time replenishment and ti..
Find the minimum dimensions for the receiving area. : The weekly average number of incoming palletized load units at the SISA DC at Gioia Tauro in Italy is 21 465. The average time needed to unload a vehicle is 18.3 minutes.  Find the minimum dimensions for the receiving area.
Find the production capacity of the line : Producing an item requires 6 different tasks. Let tj denote the time (in seconds) to complete task j. We have: t1 = 30, t2 = 25, t3 = 35, t4 = 40, t5 = 15, t6 = 30. You would like to divide the tasks to 4 workers to constitute a production line. Find..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd