Find the critical path of the project network

Assignment Help Data Structure & Algorithms
Reference no: EM131469530

Question: For given Example, suppose that the programmers choose not to obtain additional help to complete the project; that is, Bonner will code the modules without outside assistance.

a. In what way will this alter the project network and the precedence constraints?

b. Find the critical path of the project network you obtained in part (a). How much longer is it than the one determined in Example?

Example: Simon North and Irving Bonner, computer consultants, are considering embarking on a joint project that will involve development of a relatively small commercial software package for personal computers. The program involves scientific calculations for a specialized portion of the engineering market. North and Bonner have broken down the project into nine tasks. The first task is to undertake a market survey in order to determine exactly what the potential clientele will require and what features of the software are likely to be the most attractive. Once this stage is completed, the actual development of the programs can begin. The programming requirements fall into two broad categories: graphics and source code. Because the system will be interactive and icon driven, the first task is to identify and design the icons. After the programmers have completed the icon designs, they can proceed with the second part of the graphics development, design of the input/output screens.

These include the various menus and report generators required in the system. The second part of the project is coding the modules that do the scientific calculations. The first step is to develop a detailed flowchart of the system. After they complete the flowchart, the programmers can begin work on the modules. There are a total of four modules. The work on modules 1 and 2 can begin immediately after completion of the flowchart. Module 3 requires parts of module 1, so the work on module 3 cannot begin until module 1 is finished. The programming of module 4 cannot start until both modules 1 and 2 are completed. Once the graphics portion of the project and the modules are completed, the two separate phases of the system must be merged and the entire system tested and debugged. North has managed to obtain some funding for the project, but his source requires that the program be completed and ready to market in 25 weeks. In order to determine whether this is feasible, the two programmers have divided the project into nine indivisible tasks and have estimated the time required for each task. The list of these tasks, the times required, and the precedence relationships are given below.

1358_Task.png

Reference no: EM131469530

Questions Cloud

Business research on citizenship rules getting strict : Now a day's Australia changing rules for immigrants advantages and disadvantages: 457 visa ad and dis ad future effects on Australia
Currently in the introduction stage of product life cycle : Identify a product that is currently in the Introduction stage of the Product Life Cycle.
What event is represented by node : What group of activities will have to be completed by week 16 in order to guarantee that the project will not be delayed?
Rivals can effectively balance ethical business practices : Debate whether or not a for-profit company competing with rivals can effectively balance ethical business practices
Find the critical path of the project network : For given Example, suppose that the programmers choose not to obtain additional help to complete the project; that is, Bonner will code the modules.
The coefficient of variation measures : The coefficient of variation measures. With reduced demand uncertainty, a supply chain manager can. Seasonal demand can be met by...
How are the sine and cosine curves similar : Also, answer the following question as you compare sine and cosine curves. How are sine and cosine curves similar? How are the sine and cosine curves different?
Produce an essay on use of statistics : BB108 Business Statistics Written Assignment. You are required to produce an essay on "Use of Statistics." Solve statistical problems using analytical methods
Compute the earliest starting and finishing times : For the project network pictured in Figure, List the immediate predecessors of each activity. Try to determine the critical path by enumerating all paths.

Reviews

Write a Review

Data Structure & Algorithms Questions & Answers

  Write the algorithm which takes as input npda

Write the algorithm (described informally) which takes as input NPDA A and determines whether the language of A is nonempty.

  Draw a dfd that shows how data will be stored

Draw a DFD that shows how data will be stored, processed, and transformed in the TIMS system, Draw an FDD that shows the Personal Trainer's main functions

  Implementing the banker algorithm

Prompt user to enter the size of matrix n and m. Your program should accept any n x m matrix and m vectors where n and m are positive integer less than ten.

  Design a recursive linear-time algorithm

Design a recursive linear-time algorithm that tests whether a binary tree satisfies the search tree order property at every node.

  Distinguish between synchronous and asynchronous

Distinguish between synchronous and Asynchronous TDM.Compare space-division and time-division switches.What are the two approaches of packet switching? Explain them.

  Evaluate the asymptotic complexity

Evaluate the asymptotic complexity (Big Theta) int terms of n (not sum) for the given code fragment in the average case.

  Shell scripting based questions

Determine will the following only print the text "I FOUND A MATCH" to standard output when the grep is successful? if grep "mrichard" /etc/passwd; then echo "I FOUND A MATCH"; fi

  Prepare a flowchart chart to print the largest number

Write a flow chart to print the largest of any three numbers - Prepare a flowchart chart to print the largest number.

  Creating a class for services

Make a class for services offered by a hair styling salon. Information fields with a String to hold the service description, a double to hold the price, and an integer to hold average number of minutes it takes to perform the service.

  Write algorithm to calculate the median using queries

Calculate the median using as few queries as possible. Provide an algorithm which determines the median value using at most O(lg n) queries.

  Design class diagram for the customerand event classes

ICT310 - Prepare a Design class diagram for the Customerand Event classes ONLY. These two classes should be part of the Domain model class diagram solution for the previous question.

  What happens to the rms error for the validation data

What happens to the RMS error for the training data as the number of epochs increases - what happens to the RMS error for the validation data?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd