Quantitative analysis:Networks, PERT, critical path. help
Company X has been told to install some new equipment. The company has 16 weeks to install the equipment. Using the following information:
IMMEDIATE ACTIVITY TIMESACTIVITY PREDECESSORS a m b
A --- 1 2 3B --- 2 3 4C A 1 2 3D B 2 4 6E C 1 4 7F C 1 2 9G D, E 3 4 11H F, G 1 2 3
1.) What is the Critical Path?
2.) What is the expected completion time?
3.) Which activities have slack time and what are their respected slack times?
4.) What is the probability that the project can be completed in 16 weeks? (Show Work)
Determine the critical path and project duration.
A sufficiently detailed Statement of Work (SOW) can assist with the negotiations during the bidding process as well as deal with potential conflicts during the execution of the contract. Prepare a Statement of Work with at least 8 sections.
ake a research project to address this problem that focuses on the kind of research design you would use.
Identify additional stakeholders of the project and determine how they are impacted by the project.
List and explain two techniques for risk identification, such as brainstorming, a Work Breakdown Structure or a scenario analysis.
Depreciation is computed using MACRS over a 5 year life, and the cost of capital is 10%. The applicable depreciation rates are 0.20, 0.32, 0.19, 0.12, 0.11, and 0.06. Assume a 40% tax rate.
What are the five reasons productivity is difficult to improve in the service sector?
Identify the applicable decision concepts (theories, principles, paradoxes, etc.) from our learning all semester (not just the group decision concepts identified in Unit 5) that your group believes.
The company uses straight-line depreciation to a zero book value over the life of the project. The tax rate is 35%.
Analyze how HR can be used effectively to work cohesively with an organization's business strategy and explain what steps you could take to ensure flawless execution.
Project Scheduling Techniques - what are the implications of this regarding usage of any standard project scheduling technique
List 7 situations in which a manager's actions either indirectly or directly affect a guest's dining experience.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd