A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.

Reference no: EM131050196

Questions Cloud

What do we mean by computer security : How could individual proposals for resolving privacy problems be combined into a comprehensive proposal for resolving privacy issues in the era of cybertechnology?
Estimate the schedule and cost variances : Estimate the schedule and cost variances.
Calculate the wacc above the re break point : XYX corporation's capital structure calls for 60% debt and 40% common equity. The company's cost of debt is 8%. Retained earnings are estimated to be $160 million. The company's cost of retained earnings is 14% and the cost of external common equ..
Write a function that relates the amount of money you have : Write a function that relates the amount of money you have after t years. How much money will you have after 8 years? How long will it take for your money to double?
Find the cost and schedule variances and the three indexes : Find the cost and schedule variances and the three indexes.
Explain the logic behind conclusion : It has been shown that in the absence of taxes and other market imperfections firm value will be unaffected by dividend policy. Explain the logic behind this conclusion.
99 percent confidence interval around the mean : The following sample of size 11 was taken from a population that is not normally distributed: 87 59 77 65 98 90 84 56 75 96 66
Calculate the cost and schedule variances : calculate the cost and schedule variances. Will the client be pleased or angry?
Effective interest rate be for these loans : The 2ndTD is for $125,000 @ 7.5% interest, 30/15 and the 3rd. TD is for $25,000 @ 9.0% interest only for 5 years. You are to work up the payment for all 3loans. Plus, what would the "effective" interest rate be for these loans?

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Functions involving double hash on c++

Functions involving double hash on c++

  Discuss how the use of computers and technology have change

The four management tasks (planning, organizing, directing, and evaluating) existed long before computers.

  Division of the banana tree travel agency

The Surfing Shoppe lab is a division of the Banana Tree Travel Agency. The small lab has recently expanded to seven computers and is trying to design and layout their network across their two-room facility.

  Write a program that prompts the user for a measurement

write a program that prompts the user for a measurement in meters and then converts it to miles, feet and inches.

  Draw a flowchart and write the pseudocode

Draw a flowchart and write the pseudocode - calculate the average grade for each class and how many student''s grades are above and below that average.

  Use social media in a job search

You are writing up your weekly responses for your COM106 course and want to respond to a classmate who discusses the need to use social media in a job search.You are not familiar with this phrase.

  When a language has the capability to produce new data types

When a language has the capability to produce new data types, it is said to be

  Find the largest storage capacity design

Find the tallest water tower design, h . Find the largest storage capacity design. Find four other Pareto solutions that are significantly different from any other design you have obtained. How do you compare your designs to decide the extent to whic..

  Intrusion detection system (ids), and authentication server.

Using the network diagram below, your task is to incorporate the devices on the lower right into the diagram to create a secure corporate network. The devices you need to incorporate into the network diagram include: Web server, ftp server, vulnerabi..

  Difference between a wireframe mock-up and prototype

Explain the difference between a wireframe, mock-up and prototype. When might you use each?

  Perform four unconstrained optimizations

Perform four unconstrained optimizations using the following values for the penalty parameter: R = 1 , 0 . 1 , 0 . 01, and 0 . 001.

  Steps program required to search for data value

Display a message whether the user input has been found in the array, at what position, and how many steps the program required to search for the data value.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd