Find scheduling times and total slack for all activities

Assignment Help Basic Computer Science
Reference no: EM131248772

A construction firm has been commissioned to renew a portion of the Alaska crude-oil pipeline that has fallen into a state of disrepair. The project activities with the estimated times and their relationships are shown below:

1209_49ef8091-2991-4259-ac92-e61285304a91.png

a. Prepare a project network.

b. List the critical path activities and the expected project duration.

c. Determine the scheduling times and total slack for all activities.

d. In the contract, a bonus of $100,000 per day will be paid for each day the project is completed earlier than its expected duration. Evaluate the following alternatives to shorten the project duration and then make a recommendation:

1. Crash activity B by 4 days at a cost of $100,000.

2. Crash activity G by 1 day at a cost of $50,000.

3. Crash activity O by 2 days at a cost of $150,000.

4. Crash activity O by 2 days by drawing resources from activity N, thereby extending the time of N by 2 days.

Reference no: EM131248772

Questions Cloud

Ethical issues of the movie margin call : What are the ethical issues of the movie margin call?
Create a fun training environment : Tim Trainer is asked to create a fun training environment. The business leader wants the employees to enjoy their working life and make sure that they feel fulfilled and rewarded at the after a training experience -- the key to improved performanc..
Make a recommendation for one common pto system : Identify any additional information you would need to recommend a solution, and explain where you would likely find that information. Discuss any issues you would likely encounter if you were to merge the PTO system to a traditional leave system...
Find two examples of businesses in your local community : Find two examples of businesses in your local community that attempt to disclaim liability for damage to or loss of bailed property (usually, the disclaimer is in the form of a sign behind a cash register, or language on a ticket stub.)
Find scheduling times and total slack for all activities : In the contract, a bonus of $100,000 per day will be paid for each day the project is completed earlier than its expected duration. Evaluate the following alternatives to shorten the project duration and then make a recommendation
Find the bcnf of clinicplus and compare with bcnf of clinic : Suppose Clinic is augmented to ClinicPlus by the addition of the attribute Appointment, which is unique for every tuple. - This can serve as a primary key. Find the BCNF of ClinicPlus and compare it with the BCNF of Clinic.
Information systems vulnerable to destruction : Why are information systems vulnerable to destruction, error, and abuse?
Manage global team communication using technology : Write a 1,050- to 1,400-word paper that describes how you would manage global team communication using technology.
Provides an introduction to research methods and methedology : In this video, Dr Greg Martin provides an introduction to research methods, methedology and study design. Specifically he takes a look at qualitative and quantitative research methods including case control studies, cohort studies, observational r..

Reviews

Write a Review

Basic Computer Science Questions & Answers

  Identifies the cost of computer

identifies the cost of computer components to configure a computer system (including all peripheral devices where needed) for use in one of the following four situations:

  Input devices

Compare how the gestures data is generated and represented for interpretation in each of the following input devices. In your comparison, consider the data formats (radio waves, electrical signal, sound, etc.), device drivers, operating systems suppo..

  Cores on computer systems

Assignment : Cores on Computer Systems:  Differentiate between multiprocessor systems and many-core systems in terms of power efficiency, cost benefit analysis, instructions processing efficiency, and packaging form factors.

  Prepare an annual budget in an excel spreadsheet

Prepare working solutions in Excel that will manage the annual budget

  Write a research paper in relation to a software design

Research paper in relation to a Software Design related topic

  Describe the forest, domain, ou, and trust configuration

Describe the forest, domain, OU, and trust configuration for Bluesky. Include a chart or diagram of the current configuration. Currently Bluesky has a single domain and default OU structure.

  Construct a truth table for the boolean expression

Construct a truth table for the Boolean expressions ABC + A'B'C' ABC + AB'C' + A'B'C' A(BC' + B'C)

  Evaluate the cost of materials

Evaluate the cost of materials

  The marie simulator

Depending on how comfortable you are with using the MARIE simulator after reading

  What is the main advantage of using master pages

What is the main advantage of using master pages. Explain the purpose and advantage of using styles.

  Describe the three fundamental models of distributed systems

Explain the two approaches to packet delivery by the network layer in Distributed Systems. Describe the three fundamental models of Distributed Systems

  Distinguish between caching and buffering

Distinguish between caching and buffering The failure model defines the ways in which failure may occur in order to provide an understanding of the effects of failure. Give one type of failure with a brief description of the failure

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd