Find schedule variance for a project that has an actual cost

Assignment Help Project Management
Reference no: EM13852091

General Instructions: Submit your answers on a separate sheet of paper and submit through Blackboard

1.

a. Find the schedule variance for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

b. A project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and value completed of $39,000. Find the schedule and cost variances.

c. A project at day 70 exhibits an actual cost of $78,000, a scheduled cost of $84,000, and a value completed of $81,000. Find the schedule and cost indices.

2.    Consider the information about a project plan in the following table.

Task

Immediate

Predecessor

Duration

Scheduled

Cost/Day

A

-

3

$1,000

B

-

5

$2,000

C

A

4

$4,000

D

B

7

$1,000

E

C

6

$2,000

F

D

8

$3,000

The following table shows the weekly control reports for the first two weeks (assume 5 working days each week).

 

End of Week 1

End of Week 2

Task

Actual %

Completed

Cumulative

Actual Cost

Actual %

Completed

Cumulative

Actual Cost

A

60%

$1,500

100%

$ 2,900

B

30%

$3,000

100%

$11,000

C

10%

$2,000

100%

$13,500

D

0%

$        0

90%

$10,000

E

0%

$        0

50%

$ 4,000

F

0%

$        0

0%

$        0

a. Use the earned value approach to calculate BCWP, BCWS, ACWP, SV, CV, SI, and CI for each task and the whole project at Week1.

b. Calculate the total variance and time variance for the project at the end of week 2.

c. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 1.

d. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 2.

3. A manufacturer of communication systems currently overhauls its computerized payroll system. Instead of using LOC (lines of code) to track the effort on devel­oping such a payroll system, the manufacturer adopts a more reliable method, function point analysis, for measuring/monitoring the progress of the project.

The new payroll system consists of eight modules, each with a certain amount of function points. From the manufacturer's experience, each function point takes one week to develop. The ongoing project is evaluated at the end of the eighth week after its start.  The schedule/cost report is provided in the follow­ing table. (Assume linearity of cost vs. function point in each module.)

Comment on the status of the project at the end of week 8 based on the calculation of the project BCWP, BCWS, and ACWP. Is the project "in control"?; if not, why not?

Module

Immediate
Predecessors

Function
Points

Budget
(K)

Completed
Function Point

Money Spent
(K)

A

 

4

$90

4

$110

B

A

3

$65

3

$ 35

C

A

6

$75

2

$ 40

D

B

3

$60

3

$ 75

E

C

8

$55

1

$ 20

F

C

2

$40

1

$ 10

G

D, E

5

$80

0

$ 0

H

F

7

$90

0

$ 0

4.   Sandy Point is the project manager of a small project that consists of seven tasks. After careful and extensive planning, Sandy and her project staff agreed on a proposed project schedule that is indicated by the following Gantt chart:

1503_Chart.png

As indicated in their original project plan, Sandy and her staff had estimated the following durations and (total) direct costs for each task:

Task

Duration (weeks)

Planned Value

A

4

$2800

B

7

$2800

C

3

$1150

D

5

$625

E

5

$1350

F

3

$1050

G

3

$270

This morning (beginning of week 6), Sandy received a progress report; as indicated in the Gantt chart, task C could not be started until this week due to the unexpected delay in completing task A. The report also indicates that task B has been completed two weeks earlier than expected. Information from the progress report is summarized in the following table.

Task

Current

Status

Actual

Expenditures

to Date

Percent of

Work

Completed

A

Completed

$2,000

100%

B

Completed

$2,800

100%

C

Just started

$        0

0%

D

In progress

$ 330

55%

E

Not started

$        0

0%

F

Not started

$        0

0%

G

Not started

$        0

0%

a. As of today (beginning of week 6), what is the cost variance of the proj­ect?   What is the schedule variance of the project?

b. Based on information provided to date, what is your assessment of the cur­rent status of the project?

Reference no: EM13852091

Questions Cloud

Search and set up the national parks database : create a table named Park. Accept the default ID primary key field with the AutoNumber data type, renaming it as Park ID. Enter at least five additional fields, such as Name, State, Fee, Hours
High equipment rental fee keeps generating big profits : Snow peak Ski Resort offers a price for a lift ticket that is barely over its marginal cost, but the high equipment rental fee keeps generating big profits. Which pricing strategy is the management using?
Acceleration of the block along the surface : A block of mass 4.0 kg is sitting on a frhorizontal ictionless surface and is pulled with a rope that makes an angle of 30 with the horizontal, as shown in the drawing below. The tension in the rope is 25 N. What is the acceleration of the block a..
How fast are they moving now : The masses shown in the figure begin from rest and then move downwards a distance of 2.0 m. How fast are they moving now? There is no friction and the pulley has no mass.
Find schedule variance for a project that has an actual cost : Find the schedule variance for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.
Determine amount that each of those uniform payments : A person signs an agreement to offer personal services over a period of five years. The company that hires him, offered to pay him an advance of $30,000 for his professional services at the moment of signing the contract and five additional payments ..
The short run is defined as the time frame : The short run is defined as the time frame:
A risk-neutral individual would : A risk-neutral individual would:
Consumer spends more time searching for good : A consumer spends more time searching for a good when her reservation price is:

Reviews

Write a Review

Project Management Questions & Answers

  Create a project schedule and align resources

Create a project schedule and align resources, Analyze project schedule and resource allocation

  Managerial roles and gap analysis

Write a report on Managerial Roles and Gap Analysis

  Questionaire on project management

Questionaire on Project Management

  Describe the market growth rate for product

Describe the market growth rate for product and service.

  Prepare a work plan and project schedule - gantt chart

Design an online system for the human resources department to manage available job positions.

  Project risk management approach

How does a project risk management approach pro-vide an early warning signal for impending problems or issues

  Black-scholes options pricing model

Calculate the payoff and the profits for investments

  Describe the features or characteristics of product

Describe the features or characteristics of your product or service.

  Write paper on inventory management system

Write paper on Inventory Management System.

  Analysis of the overall project risk

Analysis of the overall project risk

  Investment and performance analysis

Evaluate the usefulness of ROCE

  Distribution strategy and project management

Distribution strategy and project management

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd