A project consists of replacing the track on an existing railroad line, involving 3,000 feet of track. The old track can be removed at a rate of 70 feet per hour. The old railroad ties can be removed at a rate of 200 feet (measured along the track) per hour. The new ties can be installed at a rate of 25 feet per hour, and the replacement track can be installed at a rate of 40 feet per hour. Show this operation on a linear schedule. Assume that the minimum float (buffer) for an activity at any location is 1 day.

Graph your answers. Label both the x and y axes with the units. Label the start and end times of each task.

Reference no: EM132637329

Questions Cloud

Discuss the themes and barriers that arose as a result : Discuss the themes and barriers that arose as a result of implementation to the policy. Provide support/recommendations for how the policy could be improved.
Calculate the total measurement error : a) Calculate the total measurement error if the interior angles must add up to 180°
When should use the item of that the full absorption cost : When should use the item of that The full absorption cost of the opening finished goods inventory in Preparing Operating Budgets sheet?
How would these accounts change in response : How would these accounts change in response to a 10 percent stock dividend? Assume market value of equity is equal to book value of equity
Find operation on a linear schedule : A project consists of replacing the track on an existing railroad line, involving 3,000 feet of track. The old track can be removed
Service level agreements : Cloud-based assets include any resources accessed via the cloud. Storing data in the cloud increases risks so additional steps may be necessary to protect
Selecting the best material for a particular application : 1. Describe and provide examples of factors 5 that engineers need to consider when selecting the best material for a particular application?
What knowledge did you gain about the group : What knowledge did you gain about this group that you were not aware of? Identify at least two ethical healthcare issues might arise when caring for this.
Business process redesign : Discuss what went right during the redesign and what went wrong from your perspective

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate the partial pressure of chlordane

Calculate the partial pressure of chlordane. The molecular formula for chlordane is C10Cl8H6.The average air temperature through the period of measurement was -5°C.

  How can each of these forces be neutralized

How can each of these forces be neutralized?

  Calculate all forces acting on member cdb

Contain at least one two-force member. Solve by utilizing the two-force principle, where appropriate. If the weight of a body is not specifically stated, it can be neglected. Calculate all forces acting on member CDB.

  Determine what will go into freezing the ice

You try to freeze one liter of water at 10 degrees Celsius in ice trays in your freezer. Your freezer has a coefficient of performance of 5.5 and a power rating of 550 Watts, though only 10% of the power will go into freezing the ice.

  Find corresponding racing speed and drag on the car

A one tenth scale model of a soap box derby car is tested in a wind tunnel. The air speed in the wind tunnel is 70m/s, the air drag on the model car is 240 N, and the air temperature and pressure are identical to those expected

  What is the major advantage of a dual-media coal-sand filter

What is the major advantage of a dual-media coal-sand filter compared with aconventional sand filter?

  What landfill area will be required for solid waste disposal

Solid waste will be applied in 0.6 m "lifts" and will be compacted to a depth of 0.3 m. Daily cover soil will be applied to a depth of 0.15 m for the first four days of the operation in any week. At the end of the fifth day, a "weekly cover" layer..

  What kind of microorganism is most readily inactivated

Define the meaningof C•t product. In addition to Cand t, what factors influence the rate of chemical disinfection? What kind of microorganism is most readily inactivated byfree chlorine? What kind is most difficultto inactivate?

  Design an interior setting from residential domestic waste

design an interior setting from residential domestic waste by using the methods of reuse, recycle and up-cycling which creates environment friendly atmosphere.

  Determine the required minimum diameter d of the post

determine the required minimum diameter d of the post to the nearest 1/8 in. so that it will not yield when it is struck by the block.

  Explain which is 625 feet long connects two bodies of water

A pump is to be used to draw seawater from the bay at an elevation of 0 to a reservoir at a desalination plant that has a water surface elevation of 255 feet. A 12-inch diameter DIP pipe (CHW = 120) which is 625 feet long connects the two bodies ..

  Submit a valid design before sarting building

You must submit a valid design to me before you will receive your building materials. I will not grade your design based on whether it will support the necessary load. I am only approving it as to whether it is a design that meets the building req..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd