The following information is provided for Orbit Antenna Corp., which manufactures two products: Lo-Grain antennas and Hi-Grain antennas for use in remote areas.
Activity Cost Allocation Base
Setup $58,000 Number of setups
Machine maintenance 30,000 Number of machine hours
Total indirect manufacturing costs $88.000
Lo-Grain Hi-Grain Total
Direct labor hours 1,200 3,800 5,000
Number of setups 40 40 80
Number of machine hours 3,000 2,000 5,000
Orbit Antenna plans to produce 125 Lo-Grain and 225 Hi-Grain antennas.
Required:
Problem 1. Compute the indirect manufacturing cost per unit using direct labor hours for the single plantwide predetermined overhead allocation rate.