CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018. The contract price is P10M. However, if the cumulative inflation reaches or exceeds 25%, the contract price shall be adjusted upward by 10%. Cost escalations on the contract are probable as to recovery.
Additional information on the contract is shown below:
2018 2019
Costs incurred to date 2,400,000 4,500,000
Estimated cost at completion 6,000,000 6,000,000
Cumulative inflation rate 18% 27%
Question 1. Compute for the percentage of completion during the year 2018.
Question 2. Compute for the percentage of completion during the year 2019.
Question 3. What is the contract price in 2018?
Question 4. What is the contract price in 2019?
Question 5. What is the realized gross profit in 2018?
Question 6. What is the realized gross profit in 2019?
What is difference between budgeted and actual income
: At the end of the holiday, DRG Bakery found that it had produced 90 cookies. What is driving the difference between the budgeted income and the actual income
|
Find what is the value of the growing perpetuity
: Your Aunt has promised to leave annuity. The payments are expected to go on indefinitely and the interest rate is 9%. What is value of the growing perpetuity?
|
What could the diagnosis be for the patient
: Patient comes into the clinic with the following symptoms nausea, vomiting and diarrhea, The patient has a history of drug abuse and possible Hepatitis C.
|
Explain different interpretations of codes and regulations
: Nursing as a profession firmly depends on the ethical principles of beneficence, respect for persons, and justice. These ethical principles are the standards.
|
Find for the percentage of completion during the year
: Compute for the percentage of completion during the year 2019. CABUGERO DEVELOPMENT COMPANY., started work on a construction contract in 2018.
|
Calculate the net present value
: Calculate the Net Present Value (NPV) , correct to 2 decimal places. The recent interect rate is 4.5%
|
Human resources in health care industry
: Why is human resources in the health care industry just as important as it is in other industries? Provide an example.
|
What is the original contract price
: What is the Original Contract Price 2017? The building was estimated to be built at a total cost of P15,000,000 and is scheduled for completion.
|
How the advancement was used during the pandemic
: In this unit, you explored different types of digital divides, including geographical (urban-rural), racial, intergenerational, and international.
|